F5 June 2010 Q2b – Labour Efficiency VarianceForums › ACCA Forums › ACCA PM Performance Management Forums › F5 June 2010 Q2b – Labour Efficiency VarianceThis topic has 1 reply, 2 voices, and was last updated 13 years ago by tariqilyas.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts November 24, 2011 at 5:01 pm #50687 steven18MemberTopics: 12Replies: 5☆Hi there, Can anyone explain to me how they get the amount 57,600 hours as the standard hours amount on q2 (b) of the June 2010 exam? Thanks a lot Steve November 25, 2011 at 7:42 am #90161 tariqilyasMemberTopics: 3Replies: 5☆standard lab time is 3hrs per unit and 19200 units were produced so according to std 19200 units should take 57600 hrs(19200 * 3hrs)AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In