PMF5 June 2010 Q2b - Labour Efficiency Variance

Ssteven1814y ago
Hi there,
Can anyone explain to me how they get the amount 57,600 hours as the standard hours amount on q2 (b) of the June 2010 exam?
Thanks a lot
Steve
Ttariqilyas14y ago#1
standard lab time is 3hrs per unit and 19200 units were produced
so according to std 19200 units should take 57600 hrs(19200 * 3hrs)