i have question related to point 4. Why this cost paid to third party is not included as relevant cost?
Examiner answer is: This is a cost paid directly by Push Co to a third party. Since it is not a relevant cost for T Co, it has been excluded
i dont get it since it is clear that this cost would be incurred only if contract is undertaken..
please help
thank you
Ask the Tutor ACCA PM
december 2011 question 1
The cost will only be incurred if the contract is undertaken, but we are trying to calculate the costs that will be incurred by T Co.. When T quotes a price for the job it has to cover all the costs that T will incur.
Since the cost in point 4 is not incurred by T Co. it is not included in the list of T's costs.
(Obviously it means that Push ends up paying more - but we are not asked how much Push will end up paying to everyone)
thank you
You are welcome :-)