Cut and Stitch

Sshameela3y ago
Cut and Stitch (CS) make two types of suits using skilled tailors (labour) and a delicate and unique fabric (material). Both the tailors and the fabric are in short supply and so the accountant at CS has correctly produced a linear programming model to help decide the optimal production mix. The model is as follows: Variables: Let W = the number of work suits produced Let L = the number of lounge suits produced Constraints Tailors’ time: 7W + 5L < 3,500 (hours) – this is line T on the diagram Fabric: 2W + 2L < 1,200 (metres) – this is line F on the diagram Production of work suits: W < 400 – this is line P on the diagram Objective is to maximise contribution subject to: C = 48W + 40L On the diagram provided the accountant has correctly identified OABCD as the feasible region and point B as the optimal point. Calculate the new optimum production plan if maximum demand for W falls to 200 units. ? They have taken Line F to solve the equation stating that Line F and w=200 intersect at the optimal point. I didn't understand.
John MoffatJohn MoffatTutor3y ago#1
This is linear programming and is examinable in Paper PM. It is not examinable in Paper FM (and you have posted your question in the Paper FM forum).
Topic lockedNew replies are closed.