I have got a bit confused in question number 13 from Sept 2016 past paper.
They have said that The material price when flexed is higher than budget whilst the external environment shows that prices are reducing.
I can't understand the way in the material prices are will lead to poor performance.
please help me out with this sir!
Ask the Tutor ACCA PM
CONTROLLABILITY
They have spent more on materials than they should have spent - this indicates they are doing something wrong (i.e. poor performance).
thank you, sir!
You are very welcome :-)