Skip to content

Ask the Tutor ACCA MA

closing work in progress

Kkashaf4y ago
A firm uses job costing and recovers overheads on a direct labour cost basis. Three jobs were worked on during a period, the details of which were: Job 1 Job 2 Job 3 $ $ $ Opening work?in?progress 8,500 0 46,000 Material in period 17,150 29,025 0 Labour for period 12,500 23,000 4,500 The overheads for the period were exactly as budgeted, $140,000. Actual labour costs were also the same as budgeted. Jobs 1 and 2 were the only incomplete jobs at the end of the period. 236 What was the value of closing work?in?progress? A $81,900 B $90,175 C $140,675 D $214,425 hi can u plz explain how do i solve this one thx
John MoffatJohn MoffatTutor4y ago#1
First calculate the overheads per $ of labour. You are told what the total overheads are and what the total labour costs were. Jobs 1 and 2 were still incomplete and were therefore still work in progress, The value of Job 1 icloing work in progress is the opening work in progress, plus the material in the period, plus the labour in the period, plus the overheads (using the absorption rate as in my first sentence). It is the same working for job 2. (However, why are you attempting a question for which you do not have an answer? You should be using a Revision Kit from one of the ACCA Approved Publishers - they have answers together with the workings.)
Vvez3y ago#2
Hi good morning, I am also attempting this question and I understand the workings but how is that the calculation for closing WIP? Are we assuming that with all the work done in the month, we have not completed any units? Since we are taking the full production cost of the month for both job 1 and 2. Usually when we have closing WIP we need to calculate the completed units and deduct them? Not sure whats missing for me to understand this question.. Thanks, Sara
John MoffatJohn MoffatTutor3y ago#3
This is job costing (not process costing) and the question says that the two jobs have not been completed. It is not a question of having completed some units and not having completed other units - the whole of the job is still not complete and therefore the whole job remains work-in-progress.
Sign into reply to this topic.