PMC-V-P analysis

SSkye5y ago
Can we use non-production overhead cost to count BEP in value? Or can only production-related overhead cost be used when counting BEP? Thank you so much in advance!
John MoffatJohn MoffatTutor5y ago#1
In future you must ask in the Ask the Tutor Forum if you want me to answer. This forum is for students to help each other :-) You use all fixed costs, whether production or non-production, when calculating the breakeven point.