TTod10y ago
output 10000 units. material $35.000 labour $43.000 overhead $50.000 total cost $128.000. Material cost is variable and overhead costs are fixed up to 20.000 units. labour cost includes a supervisor's fixed salary of $11000 and the remainder is variable. What is the budget total cost for an output of 15.000 units? $150,500 $161,500 $167,000 $192,000?
HHazE10y ago#1
Answer Is 161,500 Work it one by one... first is material and it says its totally variable so get the cost per unit for it 35000/10000=3.5 labour it says there is a fixed and a variable element to it..we know the fixed is 11000 and we can get variable by subtracting fixed from 43000 to get 32000 and per unit would be 32000/10000=3.2 lastly the overheads it says are fixed totally up to 20000 units so nothing changes there Now we can work for the asked units which are 15000 so material 15000*3.5= labour 15000*3.2 + the fixed 11000 overheads doesnt change since they are fixed 50000 add them up
TTod10y ago#2
Thanks !!!
Sign into reply to this topic.