Dear Sir Could you please explain to me how do get the answers: Q48.8 why 100/120? Q49.6 how do I get standard mix costs: P is 750kg, Q is 1500 kg... Many thanks
John MoffatJohn MoffatTutor10y ago#1
Q48.8 If you look at the standard cost card, the total input of materials comes to 1.2 litres, but the expected output is 1 litre. Therefore if they input 5,750 litres they would expect to produce 1/1.2 x 5,750 litres Q49.6 (I think you mean 49.8 if you are using the current edition :-) ) In total they actually used 7,500 kg. The question says that the standard mix is 10% for P, 20% for Q, etc. So out of the 7,500 total, 10% (i.e. 750) should be P; 20% (i.e. 1,500) should be Q, and so on.