I understood how I got the $1.50 however could not understand 'the next 38,000 direct labour hours'
John MoffatJohn MoffatTutor5y ago#1
The shadow price is $1.50 because each extra hour of labour they get will mean they can produce an extra 0.25 units of Y. However once the have enough labour to produce 12,000 units of Y (together with the 10,000 units of X) they will not want to buy any more labour because the demand for Y is only 12,000 units. At that level of production they will be using 98,000 hours which is 38,000 hours more than is currently available.
PPS5y ago#2
still cannot understand how did you get to 98,000 hours (that is the 38,000 hours extra)
John MoffatJohn MoffatTutor5y ago#3
You know from the labour constraint given in the question that each unit of X takes 5 hours, and each unit of Y takes 4 hours. If they produce 10,000 units of X and 12,000 units of Y (for the reasons I have already explained). then the total labour hours is 98,000. Have you watched my lectures on linear programming?
PPS5y ago#4
Now I understand I will have a look again at the lectures
John MoffatJohn MoffatTutor5y ago#5
You are welcome :-)