Basic variance analysis 2nd lecture

EEkta6y ago
sir,i calculated the variable overhead variance like this.please tell me whether it is the right way or not?Thanks in advance actual variable overheads 87,348 less: actual at standard rate 89,000 (8900*5*2) =1652F
John MoffatJohn MoffatTutor6y ago#1
It is correct (and is what I do in my lecture). However that is the total variable overhead variance and in the exam you will be asked to analyse it. I explain the analysis in my lectures.
EEkta6y ago#2
Thankyou sir
John MoffatJohn MoffatTutor6y ago#3
You are welcome :-)