Activity level

UUsman11y ago
Hi john sir ..how r u? What is the difrnc between budgted activity/capacity and normal activity/capacity..i knw about therecticl capacity and practicl capacity levels. Thanks
John MoffatJohn MoffatTutor11y ago#1
Budgeted and normal are usually going to be the same thing. It really depends on the wording of the question if it intends them to be different.