A business uses 65,000 units of an item every year and works for 52 weeks per year. There is a delay of three weeks between placing an order for the item and receiving it.
What should be set as a reorder level to ensure that inventory arrives just it is needed?
ACCA Forums
MAAccounting for material
Why are you attempting questions for which you do not have an answer? You should be using a Revision Kit from one of the ACCA approved publishers - they have answer and explanations.
You need to calculate how many units they are using each week and then calculate how many they need to last the lead time of 3 weeks.
This is all explained in my free lectures. The lectures are a complete free course for Paper MA and cover everything needed to be able to pass the exam well.
Sign into reply to this topic.