Accounting for labour

HHaSupporter6y ago
Question 6.6 from BPP practice The normal works of A is just 36 hours per week . Then we will take( 36 hour * 3.60 )+ ( 2 hour * 1.8$ ) But the workings in the answer shown ( 38 hour * 3.60 + 2 * 1.8$ ) . Where s that "38 hour" from ? Thank you Mr John
John MoffatJohn MoffatTutor6y ago#1
The overtime worked to complete a special job was 2 hours and this is a direct cost. The normal 36 hours are a direct cost. So 38 hours are a direct cost. (The other 4 hours of overtime are an indirect cost).