ACCA Forums
PMACCA Paper PM exam was - March 2021 Exam - Instant Poll and comments
rahul6342 wrote:I think the material usage planning variance was the trips were increased from 150 to 170 per month by the board of directors and the manager was NOT part of the board so this was out of his control . So 20 trips * 2 tonnes per trip = 40 tonnes at $40 per tonne = 1600 Adverse is what I gotWhat was your operating usage variance? Because total usage variance should be 600A: (340-355) x $40 = -15 x $40 = $600A
aytashi wrote:Yeah. I got one that was confusing.legendary wrote:Material price planning variance = 1,775 Adv Material price operating variance= 710 Fav<br>Material usage planning variance = 0 (because I could not find any revised usage figure)<br>Material usage operating variance= 600 Adv
aytashi wrote:Sorry but how did you calculate 136/52 to be 34/13?? The ratio is 2.62:1 which would make sense as Liability reduced by 48% and assets reduced by 15% so the ratio would go up accordingly.aytashi wrote:This is for students who did not attend in March session.
aytashi wrote:simk wrote:Did anyone have the veggie pot question? They had asked us to calculate the cost gap and had given the cost per batch and the selling price. I read the situation multiple times but just couldn’t figure out how many units were in each batch (to be able to calculate cost per unit). What did you all do?I remember calculating the target cost like this. Knowing the $2 is the max comp 1 can charge and they operate with 20% margin, the max comp 2 would sell was £1.60, therefore for the supplier (comp 2) to earn the 15% markup on cost the max cost must be no more than 1.60x100/115= 1.39
qwert443 wrote:Hi, In the question concerning coal I have calculated the below variances as someone stated above:I Have got the same answers...!
legendary wrote:My total usage variance was 1000 A, Planning 1600A and operational 600F..rahul6342 wrote:I think the material usage planning variance was the trips were increased from 150 to 170 per month by the board of directors and the manager was NOT part of the board so this was out of his control . So 20 trips * 2 tonnes per trip = 40 tonnes at $40 per tonne = 1600 Adverse is what I got
qwert443 wrote:Hi, In the question concerning coal I have calculated the below variances as someone stated above:Exactly , that’s how I double checked .. and in discussion gave the credit to manager for saving $110F total of both operational variance
aytashi wrote:I have another MCQ question, which I couldn’t calculate. If someone did answer this question please share how you calculated it. I got confused because I didn’t know how to get budgeted number of units. Here is the question:I got this question. It was so confusing and I took a lot of time trying to find the answer. Finally I chose 240 (A) which is the material usage variance I guess. Because I remember I came across this type of question when I was doing past papers and the answer was the material usage variance.
namah1 wrote:Both companies using mark up on cost right? Not marginaytashi wrote:simk wrote:Did anyone have the veggie pot question? They had asked us to calculate the cost gap and had given the cost per batch and the selling price. I read the situation multiple times but just couldn’t figure out how many units were in each batch (to be able to calculate cost per unit). What did you all do?
rashard wrote:At some point I just decided to calculate mix variance using the formula (materials usage - yield variances. ) but still couldn't get somewhere, because both usage and mix variances use budgeted number of units. how did you calculate usage variance?aytashi wrote:I have another MCQ question, which I couldn’t calculate. If someone did answer this question please share how you calculated it. I got confused because I didn’t know how to get budgeted number of units. Here is the question:
rashard wrote:no Company 1 used 20% profit margin, and the second one used mark-upaytashi wrote:simk wrote:Did anyone have the veggie pot question? They had asked us to calculate the cost gap and had given the cost per batch and the selling price. I read the situation multiple times but just couldn’t figure out how many units were in each batch (to be able to calculate cost per unit). What did you all do?
Kevin.shah wrote:Does anyone remember the answer of Section B risk question related to Maximax and maximin.for maximax you simply select the highest number in the table. don't need to calculate EV. And for maximin you compare the smallest profits (or contributions) of each project and select the highest one.
rashard wrote:Anybody got a question on calculating ROI and RI for two divisions?OMG that was so easy and tricky at the same time. One division had higher ROI than target, and another one had RI higher than it's target. I think the main point was to distinguish the 2 in terms of assessing the performance of the manager or division. I remember I selected division west
