Teacher I have some questions to ask you more.
Q1: A business uses 65,000 units of an item every year, and works for 52 weeks per year. There is a delay of three weeks between placing an order for the item and receiving it.
What should be set as reorder level to ensure that inventory arrives just as its needed?
Q2: In a budget prepared for an output of 20,000 units, the total labour cost is $48,000. of this total, 40% is the fixed salary of a supervisor, the remainder is the variable cost of direct labor. What will the total labor cost be if the budget is flexed to 24,000 units?July 8, 2015 at 5:38 pm #260176Really thanks you teacher for answering all of my question. These question I got it from here https://www.scribd.com/doc/17836176 . In this mock exam most question were appeared on CBE test and I just trying to solve all the problem in it.