Value at risk
VaR must specify the loss or value measure, horizon, confidence level and modelling assumptions. A 95% loss VaR is a threshold exceeded in roughly 5% of modelled outcomes; it is not the largest possible loss or a prediction that the threshold will occur. For project appraisal, normal-distribution calculations may express downside variation from expected NPV or a lower-tail NPV, which are different quantities. Tail shape, dependence and parameter estimates affect reliability. A normal or square-root-of-time approximation requires assumptions that may fail, especially in stressed markets.
Worked example
Expected project NPV is $20 million with standard deviation $5 million under a normal model. The 5th-percentile NPV is approximately $20m − 1.645×$5m = $11.775m. The downside distance from the mean is $8.225m; neither figure is an absolute maximum loss.
Common mistake
Describing VaR as a guaranteed worst-case limit, or confusing a lower-tail project value with the loss measured from an expected value.
Where it appears in your exams
| Qualification | Exam | Relationship | Period |
|---|---|---|---|
| ACCA | AFM | Direct | September 2026–June 2027 |