Project scope

Project scope defines what the project will deliver and the boundaries of the work required. It helps distinguish included outputs and requirements from exclusions, and provides a basis for acceptance and change control. Clear scope reduces misunderstandings but may need authorised revision when justified by new information. Uncontrolled additions can affect time, cost, resources and quality.

Worked example

A system project includes invoicing and receivables but excludes payroll. A request to add payroll is assessed as a scope change, with its effects on budget, schedule and benefits reviewed before approval.

Common mistake

Do not assume that a request is costless because it sounds small. Also distinguish what must be delivered from the detailed sequence of activities used to deliver it.