Flexed budget
A flexed budget is the budget recalculated for the actual level of activity, using the relevant budgeted prices, rates and cost-behaviour assumptions. It provides a fairer comparison with actual results than a budget at another activity level. It does not replace actual costs with budget figures; it establishes the allowed revenue or cost for the output achieved. Distinguish this activity adjustment from revising outdated standards or assumptions for planning-variance analysis.
Worked example
Actual output is 1,200 units. At budgeted variable cost $4 per unit and fixed cost $2,000, flexed cost is $6,800. Actual $7,100 gives an adverse $300 cost difference.
Common mistake
Do not flex fixed cost automatically in proportion to output, or use actual prices when the comparison requires budgeted rates.