Cost unit

A cost unit is the unit of output or service for which cost is calculated. It may be a physical item, a batch, a job or a composite measure such as passenger-kilometre. Choose a measure reflecting the service and purpose of the report. Cost per unit equals the relevant total cost divided by the number of comparable units, using a consistent period and level of completion.

Worked example

A transport service costs $50,000 and supplies 250,000 passenger-kilometres. Cost is $0.20 per passenger-kilometre.

Common mistake

Do not divide by a convenient measure that ignores an important service dimension, or mix completed units with partly completed work without adjustment.

Where it appears in your exams

QualificationExamRelationshipPeriod
ACCA MA Direct September 2026–June 2027
FIA FMA Direct September 2026–June 2027