Cost pool
A cost pool groups costs associated with an activity or other defined purpose before assignment to cost objects. In ABC, costs such as set-up staff, supplies and relevant equipment may be collected in a set-up pool and divided by an appropriate driver quantity. Pools should be sufficiently homogeneous for the driver to explain their consumption. Excessive aggregation can distort costs, while too many pools can make the system expensive and difficult to maintain.
Worked example
An order-processing pool costs $80,000 for 4,000 comparable orders, giving $20 per order before assigning costs to customers.
Common mistake
Do not mix unrelated activities in one pool merely because they are recorded in the same ledger expense account.