Cost hierarchy
A cost hierarchy groups activities by what triggers them, commonly unit-level, batch-level, product-sustaining and facility-sustaining activities. It explains why production volume alone may not describe overhead consumption. A batch activity can be incurred once regardless of batch size, while product-support effort may relate to maintaining a range. The classification helps select drivers and interpret cost reductions, but resource commitments still determine how quickly spending can change.
Worked example
Machine power may vary by unit-hours, set-ups by batches, design support by products and factory security by the facility.
Common mistake
Dividing every hierarchy level by units can hide the cost of complexity or imply facility cost disappears when one product is dropped.
Where it appears in your exams
| Qualification | Exam | Relationship | Period |
|---|---|---|---|
| ACCA | PM | Direct | September 2026–June 2027 |
