Activity-based costing

Activity-based costing assigns overhead to activity cost pools and then to products, services or customers using drivers reflecting their consumption of those activities. It can reveal cost differences hidden by a single volume-based rate, especially where batch complexity and support work vary. It does not turn an indirect cost into an objectively direct cost or guarantee accuracy: useful pools, drivers and data are essential, and the benefit must justify implementation effort.

Worked example

A set-up pool of $30,000 supports 100 set-ups, giving $300 per set-up. A product requiring eight set-ups receives $2,400, regardless of whether its unit volume is large or small.

Common mistake

ABC is not automatically more accurate or relevant for every decision; allocated unused capacity may not be avoidable cash cost.

Where it appears in your exams

QualificationExamRelationshipPeriod
ACCA APM Direct September 2026–June 2027
ACCA MA Direct September 2026–June 2027
ACCA PM Direct September 2026–June 2027
FIA FMA Direct September 2026–June 2027