Discounted cash flow - Capital Rationing - CIMA P2

CIMA Free Mock Exam
CIMA P2 lectures Download P2 notes
YouTube video

3 Comments

  1. LSupporter
    Hello,

    In the alternatives section you work out the NPV of all four possible combinations. It appears to me there is a quicker method: calculate the NPV of A, B, C and D individually, then select the projects with the three highest NPVs. Are there circumstances when this would not be appropriate?

    Thanks
  2. Harry
    How come in part (b) of the question, we work out the NPV per $ of initial investment for the ranking - This is because for a divisible project we need to apply the Profitbability Index approach.

    but in park (c) we just use the total NPV of the three investments, not the NPV per $ of initial investment - This is because for a non-divisible project you can only invest in projects in full and no fractions.

    The rankings are different because the two approaches are independent to eachother

    Hope that helps
  3. millie4498
    Hi,

    How come in part (b) of the question, we work out the NPV per $ of initial investment for the ranking, but in park (c) we just use the total NPV of the three investments, not the NPV per $ of initial investment.

    The two different ways give different rankings, therefore different answers.