  1. John MoffatTutor
    You must ask this question in the Ask the Tutor Forum - not as a comment on a lecture :-)
  2. Etharu
    ok
  3. John MoffatTutor
    I have answered you now in the Ask the Tutor Forum :-)
  4. Etharu
    i have 2 questions-

    1)a job requires 4590 actual labour hours for completion and it is anticipated that there will be 10% of idle time.if the wage rate is $8 per hour,what is the budgeted labour cost?

    2)a job requires 380 active labour hours to complete.it is expected that there will be 5% idle time.the wage rate per hour $6 per hour.what is the labour cost?

    can u send the answers if possible with a brief explanation.