ACCA PM · Guided practice (Show me how)

Chapter 5: Throughput accounting

Throughput accounting: return per bottleneck hour, TPAR and the bottleneck

Pi plc manufactures 2 products, A and B. The cost cards are as follows:

A $B $
Selling price2528
Materials820
Labour52
Other variable costs72
Fixed costs32
Total cost2326
Profit22
Machine hours p.u.2 hrs1 hr
Maximum demand (units)20,00010,000

The total hours available are 48,000. Calculate the optimum production plan and the maximum profit on the assumption that in the short term only material costs are variable, i.e. using a throughput accounting approach, and calculate the throughput accounting ratios.

Part (d). Yam Co processes sheet metal into products A, B and C through three processes, pressing, stretching and rolling, in that order. Processing time per metre in hours: pressing A 0.5, B 0.5, C 0.4; stretching A 0.25, B 0.4, C 0.25; rolling A 0.4, B 0.25, C 0.25. The factory operates for 225,000 hours. Identify the bottleneck process.

  1. (a) Throughput and the return per machine hour

    Calculate Pi plc's throughput per unit and return per machine hour for A and B.

  2. (b) The optimum plan and profit

    Prepare Pi plc's optimum production plan and calculate its maximum profit.

  3. (c) The throughput accounting ratios

    Calculate Pi plc's cost per factory hour and throughput accounting ratio for each product.

  4. (d) Yam Co: find the bottleneck

    Calculate Yam Co's process capacities for product A and identify its bottleneck process.

Opening this exercise…