James has estimated an annual standard deviation of $750,000 on one of its projects, based on a normal distribution of returns. The average annual return is $2,400,000.
Estimate the value at risk (VaR) at a 95% confidence level for one year, and also over the project's life of six years. For 95% confidence the VaR is 1.645 standard deviations from the mean.
One year
Calculate James's one-year value at risk and the return James can be 95% certain of achieving in one year.
Six years
Calculate the standard deviation and value at risk over James's six-year project life, and the total return James can be 95% certain of achieving over six years.