Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant Costing
- This topic has 3 replies, 2 voices, and was last updated 5 years ago by John Moffat.
- AuthorPosts
- October 22, 2019 at 1:06 pm #550445
A special job for a customer require 8 tonnes of a material M. The company no longer uses this material regularly although it holds 3 tonnes in inventory. These originally costs $44 per tonne, and could be resold to a supplier for $35 per tonne. Alternatively these materials could be used to complete another job instead of using other materials that would cost $126 to purchase. The current price of Material M is $50 per tonne.
The company must decide whether to agree to the customer’s request for the work, and to set a price. What would be the relevant cost of Material M for this job.
Here is how I answered
Total cost =$355 (3*35)+(5*50).
This answer was different compared to mark scheme. According to them, this company needs to consider higher of $126 and (3*35) when calculating the relevant cost of the decision, therefore the final answer equals $376. This is BPP’s revision kit’s question 108 (Part C – Decision making techniques). I don’t understand why they consider a higher cost when accepting to work towards a customer request.
October 23, 2019 at 6:40 am #550478First you have to ask yourself what the company would do with the material if they did not do the special job.
They could either sell it and receive $35 per tonne (so a total of $105) or they could use it on the other job and save a total of $126.
They would prefer to use it on the other job and save $126.If instead they used it on this special job, they would not be able to save $126 and so this is the relevant cost of using it on the special job.
Given that this only related to the 3 tonnes in inventory, they other 5 tonnes needed will have to be purchased at the current price of $50 per tonne.
October 23, 2019 at 9:29 am #550492Thanks. I think I have misunderstood the question.
October 23, 2019 at 2:35 pm #550522You are welcome 🙂
- AuthorPosts
- The topic ‘Relevant Costing’ is closed to new replies.