• Skip to primary navigation
  • Skip to main content
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
    • BT
    • MA
    • FA
    • LW
    • PM
    • TX-UK
    • FR
    • AA
    • FM
    • SBL
    • AAA
    • AFM
    • APM
    • ATX
    • Dates
    • What is ACCA

Save 20% on ACCA & CIMA Books

Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>

ACCA F7 IAS 11 Construction Contracts Workings

VIVA
ACCA F7 lectures  Download F7 notes

Reader Interactions

Comments

  1. AvatarAdrianButterfield says

    March 16, 2024 at 7:07 pm

    https://opentuition.com/acca/f7/ias-11-construction-contracts-workings/

    Log in to Reply
  2. Avatarmianmuhammdumer says

    March 26, 2016 at 11:52 am

    Great lesson. 🙂
    thanks for it.

    M Umer

    Log in to Reply
  3. Avatarsamh says

    November 30, 2015 at 7:21 pm

    Sir, can I say that the total amounts due from customer is the aggregated figure resulting from W2 and W3?

    Log in to Reply
    • AvatarMikeLittle says

      November 30, 2015 at 7:51 pm

      No, they are different in nature – show two separate figures

      Log in to Reply
  4. Avatar6shahir says

    August 15, 2015 at 8:14 am

    which question are u doing here sir?

    Log in to Reply
    • AvatarMikeLittle says

      August 15, 2015 at 8:26 am

      Up as far as 18.10 it’s just me explaining the workings and than, at 18.10 the students started on Example 2 from the course notes

      Log in to Reply
  5. Avatarsheha says

    March 23, 2015 at 3:13 pm

    Hi Sir,
    I can understand the logic of comparing cummulative revenue to recognise in SOCI for an accounting year for contracts more than a year. But I couldnt understand the recognition of cost. I understand that cost incurred for a year specifically must be fully recognised. However, I couldnt understand the part about general cost. Revenue figure used is the comparison for 2 consecutive years and the same goes for the cost right? But it doesnt make sense to compare the estimated cost for completion for year 1 with the cost in year 2. Could you please explain using the example 5 in the course notes?

    Log in to Reply
    • AvatarMikeLittle says

      March 23, 2015 at 4:29 pm

      The cost in year 2 is also estimated cost to complete. It’s the same calculation for all years. As for estimation, the whole exercise is an estimation game. Estimated stage of completion and estimated cost to complete. Both amounts are fundamental to the accounting treatment.

      But an estimate is better than saying “no revenue because we are not able to estimate stage reached” or “let’s only recognize costs to date because all the rest are estimates of future costs”

      I don’t really understand your point about “it doesn’t make sense to compare estimated cost for completion in year 1with the cost in year 2”

      Can you clarify your question for me please?

      Log in to Reply
      • Avatarsheha says

        March 23, 2015 at 4:52 pm

        Well… I basically can’t understand the answers for example 5 for the SOCI part. How to arrive to the figures in the costs recognised? I didnt have problems with year 1.

      • AvatarMikeLittle says

        March 23, 2015 at 5:59 pm

        Ah! Is this the example where a loss is forecast at the end of year 2? I believe that it is! Where a contract is forecast to be loss making, we calculate revenue in the normal way and put the figure in the top line of working one, forecast the overall loss and put that figure for forecast loss in the bottom line of working one, then complete working one by putting in the figure for expenses that, when deducted from the top line will give you the figure in the bottom line.

        Then compare that year 2 cumulative expense amount with the expense amount from year 1 and the difference is expenses recognised

        Is that better?

      • Avatarsheha says

        March 24, 2015 at 4:57 pm

        That’s better! I missed out seeing the loss forecast in year 2. Having understood that part, my ultimate question is, how do i forecast the lost in year 2 for the compared cumulative working? Perhaps I should tell you how i did my working.
        Year 2
        General cost (500 – 300+600 – 500 ) x (65%- 35%) 105
        Period cost 40
        —–
        145
        But then there’s no loss to forecast when i compare it with the revenue 1M x (65% – 35%).

        And then for year 3, my cost recognised was
        General cost 800 x 100% – 65% 280
        Period 190
        —–
        470
        And then revenue will be 1M x 35% + 200.

      • AvatarMikeLittle says

        March 24, 2015 at 6:06 pm

        Don’t do the multiplication of 65 – 35!

        Have you looked at the 5 column answer at the back of the notes?

        Work out the 65% position and then deduct the 35% column from the 65% column

        Try that and, if it’s still not hitting home, post again

      • Avatarsheha says

        March 25, 2015 at 3:55 pm

        I did. I looked at the answers already. I still can’t get it. 🙁

      • AvatarMikeLittle says

        March 25, 2015 at 6:25 pm

        Have you added together the costs to date and the estimated cost to complete? And then compared that total with the contract value?

      • AvatarMikeLittle says

        March 25, 2015 at 6:26 pm

        This thread should really be on the ask the tutor page!

    • Avatarsheha says

      June 1, 2015 at 6:33 am

      Good day Sir! I just wanted to apologise for the extremely long thread (plus this one). I ld like to let you know that I have finally understood your explanations. Not that it took me 3 months but i just took a break from this chapter and went back here with a clearer mind. Wish me luck!

      Log in to Reply
      • AvatarMikeLittle says

        June 1, 2015 at 8:31 am

        Sure I will – good luck!

  6. Avataradekunle says

    July 7, 2014 at 4:15 pm

    Sorry, whats the meaning of ”A/R” in wk 3

    Log in to Reply
    • AvatarMikeLittle says

      July 8, 2014 at 5:26 am

      Accounts receivable

      Log in to Reply
  7. Avatarhazel says

    May 11, 2014 at 9:52 am

    Hi Mike,

    Can you explain the (a) accounting treatment & the (b) impact on the % of completion of the project for:
    (1) Contract variation (ie Addition of a retractable roof of a project)
    (2) Error costs made by (2.a) the sub-contractor (ie engineer) or by the (2.b) contractor

    Hoping for your response.

    Thanks,

    Hazel

    Log in to Reply
    • AvatarMikeLittle says

      July 8, 2014 at 5:26 am

      For something as substantial as a retractable roof variation ….. at what stage of the main contract was the roof variation agreed? In practical terms I can only imagine that such a variation would result in “start again”!

      It must surely affect the engineering of the walls of the sub-structure (a stadium?)

      IF it doesn’t have that affect on the main contract but can simply be added on, then the original contract value is increased and the percentage completed calculation will be correspondingly affected

      Re error costs – if it’s an error by the engineer – I can only hope that he has good insurance. An error by a structural engineer would tend to have major financial implications. I’m thinking of recent disasters – a supermarket in Latvia, a bridge in Brazil, numerous buildings in China

      Errors by the contractor – it seems to me when I read about this type of disaster that the contractor and the engineer both very quickly leave the scene and are never heard of again – basically, they run away!

      However, on the assumption that they don’t run away, the engineer will be covered by insurance and the contractor, if solvent, will have to pay any additional costs himself

      Does that answer it?

      Log in to Reply
  8. AvatarRockstar says

    March 19, 2014 at 12:16 am

    simply great…
    Thanks Sir…

    Log in to Reply
  9. Avatartarek says

    December 13, 2013 at 9:41 pm

    Thanks Mr Mike
    Please what is mean amount invoiced ? it is amount of contract? and what different between amount due from customer in W1 and W2?
    thanks

    Log in to Reply
    • AvatarMikeLittle says

      July 8, 2014 at 5:10 am

      Amount invoiced is ……. the amount invoiced! In other words it is the amount of money received plus any outstanding invoices sent.

      The difference between “amounts due from customers” in working 2 and “amounts due from customers” in working 3 is the nature of the customers’ obligation.

      In working 2, the amount is by nature “unbilled work in progress” whereas in working 3 the amount is by nature an account receivable

      Ok?

      Log in to Reply
  10. Avatareadinnu says

    April 8, 2013 at 12:41 am

    Great and ice breaking lecture !

    Log in to Reply
  11. Avatartiamaria says

    May 16, 2012 at 7:17 am

    why after this great lecture, i am still having difficuties doing past exam papers?

    Log in to Reply
    • Avataracuteacca says

      August 27, 2012 at 3:56 pm

      @tiamaria, dear first take the third lecture of this chapter then attempt past exams or revision kit if you have difficulties then compare it with your written lecture and if further guidance required then compare with answers of questions if
      more guidance required then reply to my comment and i will solve your problem!!

      Log in to Reply

Leave a Reply Cancel reply

You must be logged in to post a comment.

Copyright © 2026 · Contact · Advertising · OpenLicense · About · Sitemap · Privacy Policy · Cookie settings · Comments · Log in