Dear Sir, Thanks for the excellent lectures. I was wondering why in example 5, for the costs recognised in year one you did not remove period specific cost of 40000 from general cost of 300000 before calculating the percentage of cost incurred that is 30% x (300000-40000+500000). I might not have understood the concept well but I think that is what you did in example 3.
In example 3 it says specifically that the $750,000 INCLUDES the $200,000 period specific
In example 5 the general costs are described as “general costs to date” and on the line above the period specific are clearly separate from those general costs.
It’s all a matter of reading the question very carefully!
Thanks for the reply.As you said is a matter of reading the question very carefully. Thanks once more for the very enriching lectures, I would also take this opportunity to thank You and Mr John Mofat for my success in CBE F2 and F3 in early september 2014. I relied solely on your lectures and revisions and i did not get any revision kit and i still scored 62 and 56 respectively. Thanks once more for the great opportunity you are giving students to pass the ACCA EXAMS.
There is this cost thing in the construction contract:
Omega has an insurance policy to protect it against claims arising on its construction contracts. The directors estimate that a monthly premium of $50,000 can reasonably be allocated to this contract, together with general administrative overheads of $40,000 per month.
So, my doubt is: Do we always take the insurance cost (if its attributed to the contract) and what about the general admin OH? The solution has not added it with other construction costs..? Any specific reason is there?
From the wording of your question, those general administrative overheads would have been incurred anyway, whether or not we were working on a contract.
Only those costs directly attributable should be involved in calculating revenue, costs and therefore profits on the contract
Here is a Dec -2008 question of Construction contract (Dipifr)
On 1 October 2007 Delta began a substantial construction project for a customer. The fixed contract price was $60 million and the estimated duration of the contract was two years. On that date they purchased plant for $15 million and materials for $10 million, both amounts being for exclusive use on the contract. They debited both amounts to the contract account that appears in the trial balance. They also used employees at a monthly cost of $500,000 throughout the 12 month period beginning on 1 October 2007. These employee costs are included in production costs in the trial balance. On 1 October 2008 Delta purchased additional materials for exclusive use on the contract at a cost of $10 million. They expect to require employees to work on the contract at a monthly cost of $400,000 for the 12 month period to 30 September 2009 but these are the only additional costs they expect to incur in future on this contract. The plant and equipment purchased for use on the contract is expected to have no residual value on 30 September 2009. The directors of Delta considered that the contract was 50% complete at 30 September 2008.
Could you please have a look if the following solution is correct?
Step1: Checking if the entire contract is profitable or loss-making:
Total contract price = 60 mn Less: Total contract costs (15+10+6+10+4.8) = 45.8 mn Total expected Profit = 60-45.8 = 14.2 (Hence, its a profit making contract)
Step2: P/L working: Revenue recognize= 50% of 60 = 30 Less: period specific costs = (500000*12)= 6 general costs= 50% [(15+10)+(10+4.8)]= 19.9
I am not sure about the ‘cost’ part. In Solutions, it says: Total expected costs: Plant: 15 Material: 10+10 Labour: 6+4.8 Total= 45.8 And, then 50% of 45.8 = 22.9 is recognised as cost of sales. But, in your lecture, it was told that we take 100% of the period specific cost.
The materials cost is not period specific ie although it was incurred specifically in that first year, it didn’t need to be – it’s just part of the overall material cost
A period specific cost is one that is incurred and that relates specifically to that particular period. Material costs are rarely specifically related to a specific period – they are merely the material costs of the entire contract.
Thank you Sir. I understand that material cost is not period specific. But what about the employee salary for that period (5,00,000 *12 months = 6mn) Wouldn’t this be considered as the period specific?
And, why plant cost is included? Don’t we just take the depreciation of plant (for 1 yr) in the costs to be recognised in P/L?
The plant has a two year life, it was bought on day 1 of the contract and dies on the completion of the contract. OK, just take the depreciation – it works out the same (because the plant was bought on day 1!)
No (employee salaries) again, like materials, employees’ wages are simply a cost of the contract. If there had had to be some remedial work and the employees had had to work specifically on repairing the previous work, that would have been period specific.
I’m going to generalise here (and I’ve never said this before (so I could be wrong!)) “a period specific cost is a cost that was not anticipated at the time the contract was started / signed but has been incurred because of some unforeseen event / circumstance”
Now, I’ve not thought that through thoroughly, but as an initial thought, it’s not bad
Great! Thanks a lot.. So, in the costs, we always take the depreciation (for that period) Why employee salary is not ‘period specific’, I have understood.
In short, I have understood it!
Thanks again. Also, you earlier asked me if I have cleared F7 or not. Actually, its my first international exam and its DipIfr. I have not given any ACCA exam prior to this. I read your F7 & P2 lectures for preparing Dipifr.
Ah, ok! It probably would have been easier if you had been an ACCA student that had already passed F7. But, no problem. It’s still there available for you to pass
Here is a Dec -2008 question of Construction contract (Dipifr)
On 1 October 2007 Delta began a substantial construction project for a customer. The fixed contract price was $60 million and the estimated duration of the contract was two years. On that date they purchased plant for $15 million and materials for $10 million, both amounts being for exclusive use on the contract. They debited both amounts to the contract account that appears in the trial balance. They also used employees at a monthly cost of $500,000 throughout the 12 month period beginning on 1 October 2007. These employee costs are included in production costs in the trial balance. On 1 October 2008 Delta purchased additional materials for exclusive use on the contract at a cost of $10 million. They expect to require employees to work on the contract at a monthly cost of $400,000 for the 12 month period to 30 September 2009 but these are the only additional costs they expect to incur in future on this contract. The plant and equipment purchased for use on the contract is expected to have no residual value on 30 September 2009. The directors of Delta considered that the contract was 50% complete at 30 September 2008.
Could you please have a look if the following solution is correct?
Step1: Checking if the entire contract is profitable or loss-making:
Total contract price = 60 mn Less: Total contract costs (15+10+6+10+4.8) = 45.8 mn Total expected Profit = 60-45.8 = 14.2 (Hence, its a profit making contract)
Step2: P/L working: Revenue recognize= 50% of 60 = 30 Less: period specific costs = (500000*12)= 6 general costs= 50% [(15+10)+(10+4.8)]= 19.9
yr1: costs to date : 300,000 +Est’d costs: 500,000 = 800,000 800,000 x 30% = 240,000
yr2: we estimated a loss =1,000,000 – (600,000+500,000) = (100,000) plus the specific periode (40,000) we’ll have a (140,000) so,Rev 650,000 spec cost (40,000) gen costs ( since we estimated a loss then this will be the balancing figure) 610,000 – x = -140,000 x= 750,000 loss recognised (140,000) I hope this is clear lol xD
40,000 does NOT occur in both years! I had that problem to. The column your looking at where 40,000 appears is a cumulative column and coz 40,000 was recognised in the first year you cant recognise again in the second. I think thats right
That’s right Biggles. rcc002 – do you see the amount of 190,000? That’s also cumulative – it’s 40,000 from year 1, zero from year 2 and 150,000 from year 3
so recognition os period specifics is 40,000 in year 1, and 150,000 in year 3 giving a total of period specifics of 190,000
Hi Mike, Thanks for the lecture. However, would you advise on the right procedure because BPP apportions both revenue rec and costs rec using the %ge completion when there is Recognised loss- and any balancing figure they call it “expected loss”, unlike the approach in this example where costs would not need to be apportioned using the %ge compl. method when a loss is recognised. Reference Question, Qn50, Books of Contract, 2012 Rev Kit, pg53. Thanks in advance!
Maybe the seller wants “to receive” this buyer by performing current contract for low price and hoping that in future buyer will bring more profits in another contracts.
Or maybe next situation. Contract is signed with profit, but lately something changed (for example seller’s equipment damaged) and new expenses occur (seller know exactly that to start works under this contract he need to purchase new equipment or repair old) and seller can’t avoid performing contract (maybe penalties will much more higher than expected losses)..
Its a balancing figure. If u forsee a loss ( [ total cost of 500+600+40] > contract value 1000) u have to immediately recognize it. So 1140 -1000 is a 140 loss. Revenue of 650 was recognized, so in order to get the 140 loss. ( 650-40-750) = 140
Thanks Marilyn – it could be a bit late – the original question was posted in April so presumably Fida has already taken the exam. I just hope that they (he or she) passed! 馃檪
I need clarification. In the event of a loss, the total loss is recognised immediately. In example 4, the Cost recognised was the balancing figure whereas the Revenue recognised was worked out based on the percentage completed.
An example in Kaplan instead gave the Revenue recognised as the balancing figure and worked out the Cost recognised with the percentage completed.
Are they accepted alternative ways of treating this situation?
Hi Mike! Could you explain the presentation in the SFP when we have both amounts due to customers and from customers? Do we demonstrate separate lines in current assets and liabilities or we present one line depending on the total difference ?
@1992825amaar, The 140 loss is the figure to be recognised by THE END of year 2. But we have already recognised 20 profit in year 1. So, in order that 140 loss should be recognised by the end of year 2, we need to recognise 160 loss in year 2 to give us 140 cumulative by end year 2.
@chenchen, Because a loss is forecast and that loss should be recognised in full in the year in which it is forecast.
Therefore, we can determine the revenue figure ( 65% x 1 million ) and we know the forecast loss by simple calculation. Therefore the costs to be recognised becomes the missing figure
@kimcap28, Because, in the situation where an overall loss is forecast, the loss must be recognised in full in the year you realise that a loss will be suffered.
In order to recognise the loss in full, the bottom line of working 1 must be completed immediately after the first line. So, now we have a figure for revenue and a figure for loss recognised. The missing figure of 510,000 is therefore the value of the costs to be recognised
Yes, that is correct. I suppose possibly it COULD be a deferred asset to be invoiced after, say, 2 years – if that’s what the contract says. But, when I wrote the question, it was intended that it was a current asset
@mdadil, Well that ‘150,000’ was as a matter of fact, added to the question and hence the increase in cumulative total of period specific cost in year 3 to ‘190,000’. It seems confusing reading the text (below) as if it’s a separate cost, but actually it has already been settled in the chart above.
tikum says
Dear Sir, Thanks for the excellent lectures. I was wondering why in example 5, for the costs recognised in year one you did not remove period specific cost of 40000 from general cost of 300000 before calculating the percentage of cost incurred that is 30% x (300000-40000+500000). I might not have understood the concept well but I think that is what you did in example 3.
MikeLittle says
In example 3 it says specifically that the $750,000 INCLUDES the $200,000 period specific
In example 5 the general costs are described as “general costs to date” and on the line above the period specific are clearly separate from those general costs.
It’s all a matter of reading the question very carefully!
tikum says
Thanks.
You are right! is a matter of reading the question very carefully.
MikeLittle says
But that’s the same principle for ALL questions in ACCA exams!
tikum says
Thanks for the reply.As you said is a matter of reading the question very carefully. Thanks once more for the very enriching lectures, I would also take this opportunity to thank You and Mr John Mofat for my success in CBE F2 and F3 in early september 2014. I relied solely on your lectures and revisions and i did not get any revision kit and i still scored 62 and 56 respectively. Thanks once more for the great opportunity you are giving students to pass the ACCA EXAMS.
MikeLittle says
Hi Bertrand
Thanks for F2 and F3 should be directed at John – I’ll pass on your thanks. But remember, it was you in that exam room!
Congratulations!
Swati says
Dear Sir,
There is this cost thing in the construction contract:
Omega has an insurance policy to protect it against claims arising on its construction contracts. The directors estimate that a monthly premium of $50,000 can reasonably be allocated to this contract, together with general administrative overheads of $40,000 per month.
So, my doubt is: Do we always take the insurance cost (if its attributed to the contract)
and what about the general admin OH? The solution has not added it with other construction costs..? Any specific reason is there?
MikeLittle says
From the wording of your question, those general administrative overheads would have been incurred anyway, whether or not we were working on a contract.
Only those costs directly attributable should be involved in calculating revenue, costs and therefore profits on the contract
Swati says
Okay, thank you Sir.
Understood..
MikeLittle says
You’re welcome
Swati says
Dear Sir,
Here is a Dec -2008 question of Construction contract (Dipifr)
On 1 October 2007 Delta began a substantial construction project for a customer. The fixed contract price was $60 million and the estimated duration of the contract was two years. On that date they purchased plant for $15 million and materials for $10 million, both amounts being for exclusive use on the contract. They debited both amounts to the contract account that appears in the trial balance. They also used employees at a monthly cost of $500,000 throughout the 12 month period beginning on 1 October 2007. These employee costs are included in production costs in the trial balance.
On 1 October 2008 Delta purchased additional materials for exclusive use on the contract at a cost of $10 million. They expect to require employees to work on the contract at a monthly cost of $400,000 for the 12 month period to 30 September 2009 but these are the only additional costs they expect to incur in future on this contract. The plant and equipment purchased for use on the contract is expected to have no residual value on 30 September
2009. The directors of Delta considered that the contract was 50% complete at 30 September 2008.
Could you please have a look if the following solution is correct?
Step1: Checking if the entire contract is profitable or loss-making:
Total contract price = 60 mn
Less: Total contract costs (15+10+6+10+4.8) = 45.8 mn
Total expected Profit = 60-45.8 = 14.2 (Hence, its a profit making contract)
Step2: P/L working:
Revenue recognize= 50% of 60 = 30
Less:
period specific costs = (500000*12)= 6
general costs= 50% [(15+10)+(10+4.8)]= 19.9
=> Attributable profits= 30- (6+19.9) = 4.1
Please let me know where have I gone wrong ?
MikeLittle says
Why do you think that you have gone wrong?
Swati says
I am not sure about the ‘cost’ part. In Solutions, it says:
Total expected costs:
Plant: 15
Material: 10+10
Labour: 6+4.8
Total= 45.8
And, then 50% of 45.8 = 22.9 is recognised as cost of sales. But, in your lecture, it was told that we take 100% of the period specific cost.
Can you please explain it?
MikeLittle says
The materials cost is not period specific ie although it was incurred specifically in that first year, it didn’t need to be – it’s just part of the overall material cost
A period specific cost is one that is incurred and that relates specifically to that particular period. Material costs are rarely specifically related to a specific period – they are merely the material costs of the entire contract.
Swati says
Thank you Sir. I understand that material cost is not period specific.
But what about the employee salary for that period (5,00,000 *12 months = 6mn) Wouldn’t this be considered as the period specific?
And, why plant cost is included? Don’t we just take the depreciation of plant (for 1 yr) in the costs to be recognised in P/L?
MikeLittle says
The plant has a two year life, it was bought on day 1 of the contract and dies on the completion of the contract. OK, just take the depreciation – it works out the same (because the plant was bought on day 1!)
No (employee salaries) again, like materials, employees’ wages are simply a cost of the contract. If there had had to be some remedial work and the employees had had to work specifically on repairing the previous work, that would have been period specific.
I’m going to generalise here (and I’ve never said this before (so I could be wrong!)) “a period specific cost is a cost that was not anticipated at the time the contract was started / signed but has been incurred because of some unforeseen event / circumstance”
Now, I’ve not thought that through thoroughly, but as an initial thought, it’s not bad
OK?
Swati says
Great!
Thanks a lot..
So, in the costs, we always take the depreciation (for that period)
Why employee salary is not ‘period specific’, I have understood.
In short, I have understood it!
Thanks again.
Also, you earlier asked me if I have cleared F7 or not. Actually, its my first international exam and its DipIfr. I have not given any ACCA exam prior to this.
I read your F7 & P2 lectures for preparing Dipifr.
MikeLittle says
Ah, ok! It probably would have been easier if you had been an ACCA student that had already passed F7. But, no problem. It’s still there available for you to pass
Swati says
Dear Sir,
Here is a Dec -2008 question of Construction contract (Dipifr)
On 1 October 2007 Delta began a substantial construction project for a customer. The fixed contract price was $60 million and the estimated duration of the contract was two years. On that date they purchased plant for $15 million and materials for $10 million, both amounts being for exclusive use on the contract. They debited both amounts to the contract account that appears in the trial balance. They also used employees at a monthly cost of $500,000 throughout the 12 month period beginning on 1 October 2007. These employee costs are included in production costs in the trial balance.
On 1 October 2008 Delta purchased additional materials for exclusive use on the contract at a cost of $10 million. They expect to require employees to work on the contract at a monthly cost of $400,000 for the 12 month period to 30 September 2009 but these are the only additional costs they expect to incur in future on this contract. The plant and equipment purchased for use on the contract is expected to have no residual value on 30 September
2009. The directors of Delta considered that the contract was 50% complete at 30 September 2008.
Could you please have a look if the following solution is correct?
Step1: Checking if the entire contract is profitable or loss-making:
Total contract price = 60 mn
Less: Total contract costs (15+10+6+10+4.8) = 45.8 mn
Total expected Profit = 60-45.8 = 14.2 (Hence, its a profit making contract)
Step2: P/L working:
Revenue recognize= 50% of 60 = 30
Less:
period specific costs = (500000*12)= 6
general costs= 50% [(15+10)+(10+4.8)]= 19.9
=> Attributable profits= 30- (6+19.9) = 4.1
Please let me know where have I gone wrong ?
Ali says
SO I’m lost over here. How exactly was the cost recognized (Genera) calculated in question 5?
Thanks in advance
abodinho says
yr1: costs to date : 300,000 +Est’d costs: 500,000 = 800,000
800,000 x 30% = 240,000
yr2: we estimated a loss =1,000,000 – (600,000+500,000) = (100,000)
plus the specific periode (40,000) we’ll have a (140,000)
so,Rev 650,000
spec cost (40,000)
gen costs ( since we estimated a loss then this will be the balancing figure)
610,000 – x = -140,000
x= 750,000
loss recognised (140,000)
I hope this is clear lol xD
rcc002 says
Hi’ now i stuck in kit questions regarding ias 11
any one here who help me on skype?
rcc002 says
dear mike:
specific cost of 40.0000 occur in both first two years, but why u can’t accont it while preparing year 2 profit nd loss
biggles says
40,000 does NOT occur in both years! I had that problem to. The column your looking at where 40,000 appears is a cumulative column and coz 40,000 was recognised in the first year you cant recognise again in the second. I think thats right
MikeLittle says
That’s right Biggles.
rcc002 – do you see the amount of 190,000? That’s also cumulative – it’s 40,000 from year 1, zero from year 2 and 150,000 from year 3
so recognition os period specifics is 40,000 in year 1, and 150,000 in year 3 giving a total of period specifics of 190,000
OK?
tauraiversatile says
Hi Mike, Thanks for the lecture.
However, would you advise on the right procedure because BPP apportions both revenue rec and costs rec using the %ge completion when there is Recognised loss- and any balancing figure they call it “expected loss”, unlike the approach in this example where costs would not need to be apportioned using the %ge compl. method when a loss is recognised.
Reference Question, Qn50, Books of Contract, 2012 Rev Kit, pg53. Thanks in advance!
crye says
It’s said losses expected should be recorded even if contract hasn’t bugun.
But why would anyone even need to go that far, like … a commercial entity embarking on a loss venture?? Why?
crye says
‘bEgun’
Sangria9 says
Maybe the seller wants “to receive” this buyer by performing current contract for low price and hoping that in future buyer will bring more profits in another contracts.
Sangria9 says
Or maybe next situation. Contract is signed with profit, but lately something changed (for example seller’s equipment damaged) and new expenses occur (seller know exactly that to start works under this contract he need to purchase new equipment or repair old) and seller can’t avoid performing contract (maybe penalties will much more higher than expected losses)..
fidahussain says
hi
can any one explain how we got 750 in statement of comprehensive income in eg 5 ch13 plz
marilynlojikim says
Its a balancing figure. If u forsee a loss ( [ total cost of 500+600+40] > contract value 1000) u have to immediately recognize it. So 1140 -1000 is a 140 loss. Revenue of 650 was recognized, so in order to get the 140 loss. ( 650-40-750) = 140
Hope this helps
MikeLittle says
Thanks Marilyn – it could be a bit late – the original question was posted in April so presumably Fida has already taken the exam. I just hope that they (he or she) passed! 馃檪
tauraiversatile says
Excellent Mariyln! This requires some practise ……………its very easy to forget.
fidahussain says
HI
CAN any one explain how we got 750 in year 2 in statement of comprehensive income eg 5 ch 13 plz
eadinnu says
Good day Mike,
I need clarification. In the event of a loss, the total loss is recognised immediately. In example 4, the Cost recognised was the balancing figure whereas the Revenue recognised was worked out based on the percentage completed.
An example in Kaplan instead gave the Revenue recognised as the balancing figure and worked out the Cost recognised with the percentage completed.
Are they accepted alternative ways of treating this situation?
eadinnu says
The answer to the issue I raised is in the technical article on construction contracts in the Sept-Nov 2008 edition of the Student Accountant.
Akis says
Hi Mike! Could you explain the presentation in the SFP when we have both amounts due to customers and from customers? Do we demonstrate separate lines in current assets and liabilities or we present one line depending on the total difference ?
1992825amaar says
In Example 5 working 2 (W2) why using $140 loss in year 2 instead of the $160 from income statement (w1)??
MikeLittle says
@1992825amaar, The 140 loss is the figure to be recognised by THE END of year 2. But we have already recognised 20 profit in year 1. So, in order that 140 loss should be recognised by the end of year 2, we need to recognise 160 loss in year 2 to give us 140 cumulative by end year 2.
Better?
chenchen says
hi Mike
in year 1 we calculated the costs (300+500) by 30% stage of completion. Why did we not do the same in year 2, multiply the costs (600+500) by 65%?
MikeLittle says
@chenchen, Because a loss is forecast and that loss should be recognised in full in the year in which it is forecast.
Therefore, we can determine the revenue figure ( 65% x 1 million ) and we know the forecast loss by simple calculation. Therefore the costs to be recognised becomes the missing figure
OK?
vikki says
So 1mil is contract value less costs (500+40+600)? I’m struggling to see what figures are being used to get to the 510 on yr2 costs recognised
vikki says
Ahh I got it!
MikeLittle says
Always better when you work it out for yourself 馃檪
kimcap28 says
In example 5 page 75-how is the 510,000 in general cost shown in the year 2 income statement calculated….somehow I am not following that bit.
MikeLittle says
@kimcap28, Because, in the situation where an overall loss is forecast, the loss must be recognised in full in the year you realise that a loss will be suffered.
In order to recognise the loss in full, the bottom line of working 1 must be completed immediately after the first line. So, now we have a figure for revenue and a figure for loss recognised. The missing figure of 510,000 is therefore the value of the costs to be recognised
Better?
claudia1 says
Hi Mike…the 50 which is yet to be billed, is an asset to be included in the SOFP…..current asset! Can you confirm please???
MikeLittle says
@claudia1, Hi
Yes, that is correct. I suppose possibly it COULD be a deferred asset to be invoiced after, say, 2 years – if that’s what the contract says. But, when I wrote the question, it was intended that it was a current asset
noldis says
Good example, however I still don’t have complete understanding why unbilled amounts and A/R has the same name ” Amounts due from/to customers” 馃檪
sdehnjo says
i understand and could apply this in a 11/2hr by the way am home studying with f7 so this is my only source of help and you guys are doing a great job
mdadil says
what about the additional costs for the constructor 150,000 ?
only4testing says
@mdadil,
Maybe Specific to date costs 190,000-40,000 = 150,000
barzakh says
@mdadil, Well that ‘150,000’ was as a matter of fact, added to the question and hence the increase in cumulative total of period specific cost in year 3 to ‘190,000’.
It seems confusing reading the text (below) as if it’s a separate cost, but actually it has already been settled in the chart above.