Sir, i have a question. a company uses flexed budgets. The fixed budget last month was based on 100% activity level and showed material costs of $200k. Last months actual material cost were $120k and showed a favourable variance of $5000 when compared with the flexed budget. What was the actual level of activity last month as a %?
(answer is 62.5%) p.s i got wrong for this when doing the revision mock exam.
If actual costs had a favourable variance then the standard cost for the actual production would be 125,000. Since the original budget was 200,000, the activity level must be 125/200 = 62.5%
HI sir there one problem in Flexed budget on Variable overhead side Variable OH Per unit = $12,500 / 10,000 Units = $2 per unit if we multiply it by actual level of activity we will get $24,000 for variable overhead in flexed budget
A Co. uses Flexed Budgets:The fixed budget last month was baase on 100% Activity level and show material cost of $200,000. Last month’s actual material cost were compared with the flexed budget and show the follow:
material Actual 120,000 Variance 5000 favourable
What was the actual activity last month as a percentage
lecturer. i feel sorry for you and you might send your students to TIME OUT for not remembering the term CONTRIBUTION………..even i named the term when you asked…………
QT co. Manufactures a single product and an extract from their flexed budget for production costs is as follows. 80%. 90% Direct material. 2400. 2700 Labour. 2120. 2160 Production o/h. 4060. 4080
What would the total production cost allowance be in a budget flexed at the 83% level of activity?
I keep on getting 7121.4 which is wrong. Any help plz???????
You need to us high/low because some of the costs are variable and some of the costs are fixed.
The total cost for 80% is 2400 + 2120 + 4060 = 8580 The total cost for 90% is 2700 + 2160 + 4080 = 8940
So, the variable cost for 10% is 8940 – 8580 = 360. So the variable cost for 3% (83% – 80%) is 3/10 x 360 = 108
So the total cost for 83% is 8580 (the cost for 80%) + 108 (the extra variable cost for the extra 3%) = 8688. (there is obviously no extra fixed cost for the extra 3%)
Sir, i have a question. a company uses flexed budgets. The fixed budget last month was based on 100% activity level and showed material costs of $200k. Last months actual material cost were $120k and showed a favourable variance of $5000 when compared with the flexed budget. What was the actual level of activity last month as a %?
(answer is 62.5%)
p.s i got wrong for this when doing the revision mock exam.
If actual costs had a favourable variance then the standard cost for the actual production would be 125,000. Since the original budget was 200,000, the activity level must be 125/200 = 62.5%
HI sir there one problem in Flexed budget on Variable overhead side
Variable OH Per unit = $12,500 / 10,000 Units = $2 per unit
if we multiply it by actual level of activity we will get $24,000 for variable overhead in flexed budget
12500 / 10000 does not equal $2 !!!
I think the problem is on your side 馃檪
thank u very much once again john
this was very straightforward…… thank you 馃檪
Hi johnmoffat
A Co. uses Flexed Budgets:The fixed budget last month was baase on 100% Activity level and show material cost of
$200,000. Last month’s actual material cost were compared with the flexed budget and show the follow:
material Actual 120,000 Variance 5000 favourable
What was the actual activity last month as a percentage
Because the variance was 5000 favourable, it means that the flexed budget will show materials of 125,000.
The original budget at 200,000, and so the actual activity must have been 125,000/200,000 x 100%
Please how did you get the contribution of 12500?
lecturer.
i feel sorry for you and you might send your students to TIME OUT for not remembering the term CONTRIBUTION………..even i named the term when you asked…………
馃檪
I always have to remind people what contribution is 馃檪
The term is used in later exams also, and always many people forget what it is!
I have a question.
QT co. Manufactures a single product and an extract from their flexed budget for production costs is as follows.
80%. 90%
Direct material. 2400. 2700
Labour. 2120. 2160
Production o/h. 4060. 4080
What would the total production cost allowance be in a budget flexed at the 83% level of activity?
I keep on getting 7121.4 which is wrong. Any help plz???????
You need to us high/low because some of the costs are variable and some of the costs are fixed.
The total cost for 80% is 2400 + 2120 + 4060 = 8580
The total cost for 90% is 2700 + 2160 + 4080 = 8940
So, the variable cost for 10% is 8940 – 8580 = 360.
So the variable cost for 3% (83% – 80%) is 3/10 x 360 = 108
So the total cost for 83% is 8580 (the cost for 80%) + 108 (the extra variable cost for the extra 3%) = 8688.
(there is obviously no extra fixed cost for the extra 3%)
amazing………hats off
Very well explained. Thanks opentuition.com
Thanks a million.
bless you……
feels like a day at the spa…..sipping on some coconut water…………….REJUVENATING!!!!!thx OT!!
This is very good. i enjoyed it. God bless this teacher.
cannot find video for example 2b, please assist
thanks, great job!
Good
cleared up a whole lot of things. very good.
I cannot see this lecture. Is this meant to be audio.
@cherylcheeseman, yes
good