Comments

  1. avatar says

    Sir, i have a question. a company uses flexed budgets. The fixed budget last month was based on 100% activity level and showed material costs of $200k. Last months actual material cost were $120k and showed a favourable variance of $5000 when compared with the flexed budget. What was the actual level of activity last month as a %?

    (answer is 62.5%)
    p.s i got wrong for this when doing the revision mock exam.

  2. avatar says

    HI sir there one problem in Flexed budget on Variable overhead side
    Variable OH Per unit = $12,500 / 10,000 Units = $2 per unit
    if we multiply it by actual level of activity we will get $24,000 for variable overhead in flexed budget

  3. avatar says

    Hi johnmoffat

    A Co. uses Flexed Budgets:The fixed budget last month was baase on 100% Activity level and show material cost of
    $200,000. Last month’s actual material cost were compared with the flexed budget and show the follow:

    material Actual 120,000 Variance 5000 favourable

    What was the actual activity last month as a percentage

  4. Profile photo of m1n2b3v says

    lecturer.
    i feel sorry for you and you might send your students to TIME OUT for not remembering the term CONTRIBUTION………..even i named the term when you asked…………

  5. Profile photo of nakeshia says

    I have a question.

    QT co. Manufactures a single product and an extract from their flexed budget for production costs is as follows.
    80%. 90%
    Direct material. 2400. 2700
    Labour. 2120. 2160
    Production o/h. 4060. 4080

    What would the total production cost allowance be in a budget flexed at the 83% level of activity?

    I keep on getting 7121.4 which is wrong. Any help plz???????

    • Profile photo of John Moffat says

      You need to us high/low because some of the costs are variable and some of the costs are fixed.

      The total cost for 80% is 2400 + 2120 + 4060 = 8580
      The total cost for 90% is 2700 + 2160 + 4080 = 8940

      So, the variable cost for 10% is 8940 – 8580 = 360.
      So the variable cost for 3% (83% – 80%) is 3/10 x 360 = 108

      So the total cost for 83% is 8580 (the cost for 80%) + 108 (the extra variable cost for the extra 3%) = 8688.
      (there is obviously no extra fixed cost for the extra 3%)

Leave a Reply