• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

REVENUE FROM CONTRACTS

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › REVENUE FROM CONTRACTS

  • This topic has 8 replies, 3 voices, and was last updated 2 years ago by Eunice03.
Viewing 9 posts - 1 through 9 (of 9 total)
  • Author
    Posts
  • August 26, 2022 at 11:33 pm #664373
    Eunice03
    Participant
    • Topics: 88
    • Replies: 70
    • ☆☆

    TYU 8
    Merryview specialises in long-term contracts. In each contract
    Merryview is entitled to receive payments reflecting the progress of the
    work, so revenue should be recognised over time.
    One of its contracts, with Better Homes, is to build a complex of luxury
    flats. The price agreed for the contract is $40 million and its scheduled
    date of completion is 31 December 20X2. Details of the contract to
    31 March 20X1 are:
    Commencement date 1 July 20X0
    Contract costs: $000
    Architects’ and surveyors’ fees 500
    Materials 2,800
    Direct labour costs 3,500
    Overheads are apportioned at 40% of direct labour
    costs
    Estimated cost to complete
    (excluding depreciation – see below) 14,800
    Plant and machinery used exclusively on the contract cost $3,600,000
    on 1 July 20X0. At the end of the contract it is expected to be
    transferred to a different contract at a value of $600,000. Depreciation
    is to be based on a time-apportioned basis. Better Homes made a
    progress payment of $12,800,000 to Merryview on 31 March 20X1.
    SOLUTION
    Overall contract
    31 March
    20X1
    $000
    Price 40,000
    ––––––
    Costs to date:
    Architects’ and surveyors’ fees 500
    Materials used 2,800
    Direct labour 3,500
    Overheads (40% of 3,500) 1,400
    Depreciation
    ($3m/30 months × 9 months) 900 ––––––
    Total costs to date 9,100

    Good day sir,I don’t understand why the cost of the machine wasn’t added to the costs to date since it was used in the contract. I’ll appreciate if you can explain better

    August 30, 2022 at 9:18 am #664671
    midhunh
    Participant
    • Topics: 2
    • Replies: 2
    • ☆

    What should be done is add the cost of machine to the total cost of the contract.
    and when finding cost to date only the depreciation is to be added. the same principle of using depreciation which is allocating the cost to the period of use right. and hence only depreciation cost to be added to “cost to date”
    hope this clarifies.

    August 31, 2022 at 6:26 pm #664777
    Eunice03
    Participant
    • Topics: 88
    • Replies: 70
    • ☆☆

    Hi,isn’t the cost to date needed to calculate the overall contract cost?.In the soution, the cost of the machine was totally excluded when calculating the cost of the contract

    September 1, 2022 at 7:54 pm #664895
    P2-D2
    Keymaster
    • Topics: 4
    • Replies: 7171
    • ☆☆☆☆☆

    Hi,

    It is a funny question as usually we are given the costs to date in the question but here it is asking you to calculate them from the information given. They have done this correctly with regards to the depreciation as they have only included half of it, given we are half way through the contract. The other half of the depreciation would be part of the costs to complete that we would use to see if the contract is profitable.

    Thanks

    September 5, 2022 at 1:46 pm #665227
    Eunice03
    Participant
    • Topics: 88
    • Replies: 70
    • ☆☆

    Hi,I understand why half of the depreciation was part of the costs to date.I don’t understand why the 3,600,000 for the machinery wasn’t included in the cost to date since it was used exclusively for the contract.

    September 5, 2022 at 8:58 pm #665303
    P2-D2
    Keymaster
    • Topics: 4
    • Replies: 7171
    • ☆☆☆☆☆

    Because this is the full cost of the machinery, we only include the depreciation charged upon it to date. Check out the dates within the question, i.e. when we started the contract and the current reporting date. How many months is it?

    Thanks

    September 7, 2022 at 1:33 am #665492
    Eunice03
    Participant
    • Topics: 88
    • Replies: 70
    • ☆☆

    So the cost is excluded because it wasn’t bought at the start of the contract? For example, If the question had said that the machine was bought at the start of the contract, will the full cost be included in the cost to date?

    September 11, 2022 at 9:08 pm #666185
    P2-D2
    Keymaster
    • Topics: 4
    • Replies: 7171
    • ☆☆☆☆☆

    Yes, that’s correct. The questions need to be read very carefully as the examiners are going to try and trick you!

    Thanks!

    September 12, 2022 at 12:57 am #666191
    Eunice03
    Participant
    • Topics: 88
    • Replies: 70
    • ☆☆

    Thank you

  • Author
    Posts
Viewing 9 posts - 1 through 9 (of 9 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Ken Garrett on ACCA BT Chapter 6 – Some legal obligations – Questions
  • Ken Garrett on The nature and structure of organisations – ACCA Paper BT
  • OmarAlbeity on ACCA BT Chapter 6 – Some legal obligations – Questions
  • Salimbek909 on The nature and structure of organisations – ACCA Paper BT
  • Sefater on Chapter 3 – Property Income and Investments – Individuals TX-UK FA2023

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in