- This topic has 1 reply, 2 voices, and was last updated 5 years ago by .
Viewing 2 posts - 1 through 2 (of 2 total)
Viewing 2 posts - 1 through 2 (of 2 total)
- You must be logged in to reply to this topic.
Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › IFRS 15 — Revenue from Contracts
Dear tutor,
Regarding IFRS 15 – Revenue, i have watched your lectures and understand it quite well thanks to opentuition. However, the part where you taught how to calculate the contract asset/liabilty, is it not updated? Because, I personally attended other tuiton provider but my lecturer stated that the way you calculated them is not updated. Here is for example of what i meant.
Bridgenorth has undertaken a $5million contract to repair a railway tunnel.The contract was signed in 1 April 20X8 and the work is expected to take two years.This is a contract where performance obligations are satisfied over time and progress in satisfying performance obligations is to be measured according to % of work completed as certified by a surveyor. Bridgenorth has an enforceable right to payment for performance completed to date
At 31 December 20×9 the details of the contract were as follows
$’000
—————————————————–20×9———-x0x8
Total contract price—————————-5000——–5000
cost to date————————————-3600——–2300
estimated cost to completion————–700———-2100
work invoiced———————————3000——–2000
cash received——————————–2400——–1500
%certified complete————————–75%——-40%
What is the contract asset to be recognised at 31 December 20X9?
The answer shown is $1,1250,000. However during my lecture, it was stated that it is not updated and the answer should be $750,000.
Thank you in advance.
Hi,
I’ll have a look and see if I need to update the answer for contract asset/liability.
Thanks
