- This topic has 2 replies, 2 voices, and was last updated 5 years ago by .
Viewing 3 posts - 1 through 3 (of 3 total)
Viewing 3 posts - 1 through 3 (of 3 total)
- You must be logged in to reply to this topic.
OpenTuition recommends the new interactive BPP books for March 2025 exams.
Get your discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA SBR Exams › Verge Q31 (b) BPP Kit
Hi Sir,
I’m very muddled up on this one.
I understand the $1m would be a contract liability for the company as they have received money before completion and thus, a significant component exists. CR Contract Liability $1m and DR Cash $1m as at inception
But for the remaining amounts, I don’t understand why they are treated as significant components or discounted if the government won’t be paying the rest of the money until the end of the project when it’s completed? I would’ve done CR Rev $1.8m, DR Receivables $1.8m without time value of money
Please can you advise?
Thank you
And that would be for Y/e 31 March 20X2
Hi,
The key is that the invoices have been sent so the revenue needs to be recognised, and will be done so at its present value. We don’t wait to receive the cash to recognise the revenue.
Thanks