Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Variance – BPP pg 45/54 ASH (J’06)
- This topic has 11 replies, 4 voices, and was last updated 5 years ago by John Moffat.
- AuthorPosts
- November 23, 2012 at 8:39 am #55652
The question is as follows :
“Ash plc recorded the following actual results for Product RS8 for the last month:
Product RS8 2,100 units produced and sold for $14.50 per unit
Direct material M3 1,050 kg costing $1,680
Direct material M7 1,470 kg costing $2,793
Direct labour 525 hours costing $3,675
Variable production overhead $1,260
Fixed production overhead $4,725Standard selling price and cost data for one unit of Product RS8 is as follows.
Selling price $15.00
Direct material M3 0.6 kg at $1.55 per kg
Direct material M7 0.68 kg at $1.75 per kg
Direct labour 14 minutes at $7.20 per direct labour hour Variable production overhead $2.10 per direct labour hour
Fixed production overhead $9.00 per direct labour hourAt the start of the last month, 497 standard labour hours were budgeted for production of Product RS8. No inventories of raw materials are held.
All production of Product RS8 is soldimmediately to a single customer under a just-in-time agreement.Required:
(a) Prepare an operating statement that reconciles budgeted profit with actual profit for Product RS8 for the last month. You should calculate variances in as much detail as allowed by the information provided.”
Acc. to BPP, in order to perform the reconciliation, we first need to calc. Budgeted Profit then add n substract all variances to arrive at the actual profit.
According to the BPP ans, the calculation of the bugeted profit is :
(Std gross Profit/unit * std hrs for budgeted production.)So Std gross profit/unit = Std SP/unit – total std costs/unit
=15 – 6.39
= $ 8.61/unitWhat i don’t understand is , if std gross pr. is calculated per unit then y is budgeted gross profit calculated by multiplying std gprofit per unit by std hrs for budgeted prodn?
As per BPP ans , Budgeted gross pr. = $8.61 *497hrs* 60/14
= $18339.3Why is it not budgeted gross pr./unit * budgeted no.of unit?
November 25, 2012 at 8:18 am #108451It is budgeted units x standard gross profit, and that is what they have done.
If they budgeted on having 497 hours of labour available, and if each unit takes 14 minutes, then they must have budgeted on producing 497 x 60 / 14 units (which is what you have typed).
November 25, 2012 at 11:16 pm #108452yes right… i get it.
November 26, 2012 at 8:17 pm #108453Thats great 🙂
November 29, 2012 at 5:11 pm #108454@John Moffat. when working the question I set up the table with budgeted and actual and variance as you did in the lectures, is this Ok to do in exam?
Also, the variance from the table would be the price variance, does that mean that i dont have to show the workings for the price variance when doing the workings for the operating statement?November 29, 2012 at 5:12 pm #108455by the way i totally missed the budgeted sales in this question its when i looked at the answer that i realised that i should have used the labour hours to work it out.
November 29, 2012 at 9:24 pm #108456It is OK to set up a table as I did.
However, apart from sales, that table only gives the total variances whereas in the exam you will be required to analyse them (for example, materials expenditure and materials usage variances – not the total materials variance).
For that reason, I did say in my lecture not to waste time producing that table – I did it in the lecture to make sense of what followed. You must learn the rules for all the individual variances – you will not have time to calculate the total variance and then to start analysing it.
November 30, 2012 at 2:38 pm #108457thank you
December 1, 2012 at 6:13 pm #108458YOu are welcome 🙂
January 26, 2019 at 7:01 am #503294how to get the right calculations for sales volume profit variance?
January 26, 2019 at 7:13 am #503295@latoyah84 said:
by the way i totally missed the budgeted sales in this question its when i looked at the answer that i realised that i should have used the labour hours to work it out.do you have the answer?
January 26, 2019 at 10:23 am #503312This question is from an exam that was set nearly 13 years ago.
Preparation of an operating statement is no longer asked in Paper PM and so BPP have removed this question from their Revision Kit.
If you still want an answer then you are going to have to search for the June 2006 exam on Google. Alternatively if your Revision Kit is from one of the other publishers then you just might find it there, but I doubt it because the syllabus has changed. (I assume you have bought a Revision Kit from one of the ACCA approved publishers – practicing every question in your Revision Kit is vital to passing the exam.)
- AuthorPosts
- The topic ‘Variance – BPP pg 45/54 ASH (J’06)’ is closed to new replies.