Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › Revenue P/L
- This topic has 1 reply, 2 voices, and was last updated 1 year ago by P2-D2.
- AuthorPosts
- August 20, 2023 at 6:03 pm #690343
CN started a three?year contract to build a new university campus on 1 April 20X4. The contract had a fixed price of $90 million. CN willsatisfy the performance obligation over time. CN incurred costs to 31 March 20X5 of $77 million and estimated that a further $33 million would need to be spent to complete the contract. CN measures the progress of contracts using work completed compared to contract price. At 31 March 20X5, a surveyor valued the work completed to date at $63 million. Select the correct amounts to be shown in revenue and cost of sales in the statement of profit or loss for the year ended 31 March 20X5?
Step 1 – Overall
$m Price 90
incurred to date (77)
estimated future (33)
Overall loss (20)Step 2 – Progress Progress = work certified 63/total price 90 = 70%
Step 3 – SPL $m
Revenue (70% of 90) 63
Cost of sales (balancing figure to recognise full loss) (83)
FULL loss to be recognised immediately (20)Sir, my question is: 83 AMOUNT ?N THE PL: 77 COST TO DATE AND 6 PROVISION TO RECOGNISE LOSS? AM I RIGHT?
I was confused because of that in the book’s solution PL part didn’t deducted cost to date amount (77).
August 22, 2023 at 3:31 pm #690467Hi,
The cost to date is included within the balancing figure of 83, and we just need to accrue for the additional cost of 6 that have been incurred.
Thanks.
- AuthorPosts
- You must be logged in to reply to this topic.