• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Relevant Cost

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant Cost

  • This topic has 3 replies, 2 voices, and was last updated 4 years ago by John Moffat.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • March 1, 2021 at 5:35 pm #612414
    adhilvpd
    Member
    • Topics: 6
    • Replies: 8
    • ☆

    1.UU Company has been asked to quote for a special contract. The following information
    about the material needed has been given:
    Material X:
    Book value $5.00 per kg Scrap value$0.50 per kg Replacement cost $5.50 per kg
    The contract requires 10 kgs of Material X. There are 250 kgs of this material in inventory
    which was purchased in error over two years ago. If Material X is modified, at a cost of
    $2 per kg, it could then be used as a substitute for material Y which is in regular use and
    currently costs $6 per kg.

    2.Push Co would also need a computerised control system called ‘Swipe 2. The current market price of Swipe2 is $10,800, although T Co has an older version of the system, ‘Swipe 1’, in inventory, which could be modified at a cost of $4,600. T Co paid $5,400 for Swipe 1 when it ordered it in error two months ago and has no other use for it. The current market price of Swipe 1 is $5,450, although if T Co tried to sell the one it has, it would be deemed to be ‘used’ and therefore only worth $3,000.

    What is the difference in this two questions. In both question we have an alternate.
    In the first question, the money saved from not buying Y is taken.
    In the 2nd question, modification cost + selling cost(3000) is taken.

    I don’t find any difference in this two questions. But the answers are through different approach.
    Please clarify my doubt

    March 2, 2021 at 9:15 am #612551
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54682
    • ☆☆☆☆☆

    The questions are a lot different. They would only be similar if in the first question it was material Y that was needed for the contract, which is not the case.

    In the first one they need material X for the contract. If they were not using it in the contract they could either sell if for 0.50 per kg, or use it as a substitute for Y which would save them 6 – 2 = $4.
    They would be better using it as a substitute for Y to save $4.
    Therefore using X in the contract is losing them the $4 that they could have otherwise saved.

    In the second one, they can either buy a Swipe 2 for the contract or instead use Swipe1 and modify it. It is cheaper to use Swipe 1 (and modify it) and so this is what they will do.

    March 2, 2021 at 11:51 am #612645
    adhilvpd
    Member
    • Topics: 6
    • Replies: 8
    • ☆

    Thank you very much sir. I was stuck in this one since yesterday. I was so worried that your reply didn’t come quickly. I was checking for it in every hour. I know that you are so busy. Thank you very much sir.
    You deserve so much respect and what you are doing is unbelievable. With free of cost. I really wish to donate for Opentuition. I will definitely do it when I become an affiliate and earn some money.
    I’m going to face the exam tomorrow. Hope I will be doing good.

    March 2, 2021 at 3:34 pm #612705
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54682
    • ☆☆☆☆☆

    Thank you for your comments, and I hope the exam goes well for you tomorrow.

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • The topic ‘Relevant Cost’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • maryrena77 on The nature and structure of organisations – ACCA Paper BT
  • vi234 on MA Chapter 4 Questions Cost Classification and Behaviour
  • vi234 on MA Chapter 4 Questions Cost Classification and Behaviour
  • John Moffat on The financial management environment – ACCA Financial Management (FM)
  • Lekhanaa on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in