Identify which two of the following would be an acceptable method of measuring the performance obligations completed?
-Work invoiced to date as a percentage of total contract price -Cash received to date as a percentage of total contract price -Costs incurred as percentage of total expected costs -Time spend as percentage of total expected contract time
Can you please help me with this question. thank you.