- This topic has 0 replies, 1 voice, and was last updated 5 months ago by
thewdr.
Viewing 1 post (of 1 total)
Viewing 1 post (of 1 total)
- You must be logged in to reply to this topic.
New! BPP Books for ACCA September 2022 Exams are now available, get your discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › KAPLAN question
The sales value of the work done at 31 March 20X9 has been agreed at $22 million and
the estimated cost to complete (excluding plant depreciation) is $10 million. The
specialist plant will have no residual value at the end of the contract and should be
depreciated on a monthly basis Price well recognises progress towards satisfaction of
the performance obligation on the outputs basis as determined by the agreed work to
date compared to the total contract price
Sir what is meant by ” outputs basis as determined by the agreed work to
date compared to the total contract price”?