- This topic has 3 replies, 3 voices, and was last updated 14 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- You must be logged in to reply to this topic.
Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA SBR Exams › Contruction contract
There is a construction contract undertaken by the company near the end of the financial year ended 31/12/2011. The cost incurred up to 31/12/2011 was $30 and an advance payment of $50 was received. As the outcome of the contract cannot be estimated reliably, cost recovery method is adopted, with nil profit recognised. In that case , are the following entries correct:
In Income statement
Revenue 30
Cost incurred 30
_____
Nil
In SOFP
Gross amount due to customer
Cost incurred 30
Add Profit recognised Nil
Progess billing (50)
______
20
======
Am I correct in principle ? Would you kindly advise?
That seems correct to me 🙂
This might be a lil bit more helpfull:
Practically all these entries are passed in co’s accounts:
When Advance is received:
Cash Dr 50
Advance From customer Cr 50
When Actual Expense is incurred by the co, following entries are passed with the actual amount of expenditure:
WIP Dr 30 (Just would appear in co’s Trial Balance)***
Mat, Cash,etc Cr 30 (Assets Being credited from SOFP)
Recording revenue and exp:
Exp Dr 30 (PnL)
Rev Cr 30 (PnL)
***Now Net of WIP and Advance from Customer Would be shown in Co’s Balance sheet (20 would be shown as Due to customer in SOFP)
Hi
Not sure I can agree with Nokia’s double entries.
I would be inclined to do this:
Dr Cash 50 Cr Receivable 50
Dr Costs 30 Cr Cash 30
At the year end, Dr Receivable 30, Cr Revenue 30
These leave you with 30 revenue less 30 costs = so no profit recognised
Cash has increased by 20 and 20 is owing to the customer
