• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Contract asset

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › Contract asset

  • This topic has 10 replies, 4 voices, and was last updated 4 years ago by krishnaveni.
Viewing 11 posts - 1 through 11 (of 11 total)
  • Author
    Posts
  • September 26, 2016 at 1:26 pm #341751
    herocomesalong
    Member
    • Topics: 66
    • Replies: 36
    • ☆☆

    Hello Tutor,

    <december2013>
    Moby entered into a contract to construct an asset for a customer, performance obligation is satisfied over time. The balance in trial balance represents $14m costs incurred to date and $10m value of contract billed and cash received. Should the receivable of $10m be added to both the revenue and trade receivable amounts? The question did add it to only revenue but not to trade receivable, why is that so?

    September 26, 2016 at 1:57 pm #341757
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23319
    • ☆☆☆☆☆

    ‘The balance in trial balance represents $14m costs incurred to date and $10m value of contract billed and cash received.’

    What makes you think that the $10 million has actually been received?

    What’s the matter with …

    Dr Receivables $10m
    Cr Construction Contract account $10m

    … as the part explanation of the $4m figure in the trial balance?

    September 26, 2016 at 4:22 pm #341775
    herocomesalong
    Member
    • Topics: 66
    • Replies: 36
    • ☆☆

    Sorry, I still don’t understand a part of that

    In the June 2009 paper question 2 on Pricewell Co,
    The trial balance shows a construction contract account of $14,300, which represents
    Material etc $12,000
    Plant $8,000
    Payment from customer $(5,700)

    The sales value of the work done has been agreed at $22m and the estimated cost to complete is $10m.

    The receivable was calculated to $16,300.
    The answer added $22m to revenue (which I understand now), but added $16,300 to trade receivables (why?)

    September 26, 2016 at 8:42 pm #341801
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23319
    • ☆☆☆☆☆

    Have you followed the video lecture on this?

    The question you originally posted suggested that you believed that the $10 million had been invoiced AND PAID

    There is NOTHING in that question to say that it has been paid

    This is a different scenario from Pricewell

    Have you watched me work through the Pricewell question in the revision lectures?

    May I ask that you watch me work through Pricewell, that you watch the video lecture of construction contracts (if it’s still on the site) and then look at Moby again

    If you’re still in trouble after that, by all means post again

    September 27, 2016 at 7:24 am #341848
    herocomesalong
    Member
    • Topics: 66
    • Replies: 36
    • ☆☆

    Sorry, I have not watched all your lectures, but I just did for the revision lecture on pricewell co. Can I confirm this?:

    In moby’s scenario,
    The question did not say that customer had paid for the $10m, and the trade receivables in the trial balance had included this amount, and so no adjustments were needed.

    In pricewell’s scenario,
    It said that $5,700 had been paid for by the customer, but didn’t say that the remaining $16,300 was billed or not. And so we had to add this amount to the trade receivables account.

    Is this correct?

    September 27, 2016 at 7:33 am #341849
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23319
    • ☆☆☆☆☆

    Sounds correct

    You should watch the lecture on chapter 13 from page 72 onwards – that will show you how you arrive at the receivables figure

    You shouldn’t try to ‘memorise’ answers because questions are only rarely the same!

    September 27, 2016 at 8:18 am #341857
    herocomesalong
    Member
    • Topics: 66
    • Replies: 36
    • ☆☆

    Alright I will 🙂 guess I had misunderstood the phrase “…invoiced and cash received”, thank you!

    September 27, 2016 at 11:31 am #341874
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23319
    • ☆☆☆☆☆

    You’re welcome

    May 20, 2021 at 7:02 pm #621243
    krishnaveni
    Member
    • Topics: 0
    • Replies: 2
    • ☆

    Hi sir,

    The company recognises revenue on the basis of the costs completed as a proportion of the final contract value. the client gains the use of the asset doing its construction.

    the following details apply to a contract where performance obligations are satisfied over time at 31 December 20X5.

    Total contract revenue 120,000
    Cost to date 48,000
    Estimated costs to completion 48,000
    Amounts invoiced 50,400

    the contract is agreed to be 45% complete at 31 December 20X5.

    What amount should be recognised in the statement of financial position at 31 December 20X5 as a contract asset?

    Could you please explain the answer for this sir?
    working provided is
    120,000-48,000-48,000 = 24,000 * 45% = 10,800

    Cost incurred 48000 + 10,800 – 50,400 = 8,400 I don’t understand this part sir, kindly help to clarify.

    Thank you!

    May 22, 2021 at 9:34 am #621411
    P2-D2
    Keymaster
    • Topics: 4
    • Replies: 7163
    • ☆☆☆☆☆

    Hi,

    The 10,800 is the profit recognised through profit or loss and the 8,400 is the contract asset on the SFP.

    The profit is the percentage complete multiplied by the total profit.

    The asset is calculated as the costs to date plus profit to date less amounts invoiced.

    Thanks

    May 24, 2021 at 4:34 pm #621652
    krishnaveni
    Member
    • Topics: 0
    • Replies: 2
    • ☆

    Thank you for the prompt reply.

  • Author
    Posts
Viewing 11 posts - 1 through 11 (of 11 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • shravanm on ACCA AAA Employability and Technology Skills
  • MitaP on Presentation of Financial Statements (IAS 1) – ACCA Strategic Business Reporting (SBR) lectures
  • John Moffat on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • Shabi on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • Ark1 on Variance Analysis (part 4) – ACCA Management Accounting (MA)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in