• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

March 2026 ACCA Exams

Comments & Instant poll

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2026 exams.
Get your discount code >>

CIMA P3 Exam Practice Kit Q256 IRR

Forums › CIMA Forums › CIMA P3 Exam Practice Kit Q256 IRR

  • This topic has 5 replies, 3 voices, and was last updated 6 years ago by Ken Garrett.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • May 27, 2019 at 3:12 am #517463
    hkkwu
    Participant
    • Topics: 10
    • Replies: 5
    • ☆

    Hi tutor,

    I am confused by the answer to Q256. Why would be discount rate reduced by 1.25% the NPV would fall to zero? I thought it should be the rise in discount rate, which would make the NPV fall.

    Thanks,
    Student

    Question:
    Q Co is going to invest in a new piece of machinery that will cost $8,000,000. The discount
    rate of the project is 15% and the PV of the tax shield is $100,000.
    What is the IRR? Give your answer as a % to 2 decimal places
    _____________%

    Answer:
    256 14.81
    The IRR is the discount rate where the NPV falls to zero.
    It is a really a sensitivity calculation, the questions we need to ask ourselves are as follows:
    (1) How much would the NPV need to change by? 100,000
    (2) What is this as a % of the investment? 100,000/8,000,000 × 100 = 1.25%
    So if the discount rate reduced by 1.25% the NPV would fall to zero.
    IRR = 15% × 98.75% = 14.8125
    Answer: 14.81.

    May 27, 2019 at 8:46 am #517497
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10648
    • ☆☆☆☆☆

    It confuses me too.

    The tax shield is present value of tax relief on debt interest payments evaluated at the pre-tax cost of debt and is used in APV calculations. We are not told the NPV of the project at 15%, nor its APV (though that would be $100,000 higher than the NPV).

    The NPV could be $20,000,000 – we don’t know and the IRR of that project would be very high indeed!

    I think the whole question is messed up.

    May 27, 2019 at 9:46 am #517515
    hkkwu
    Participant
    • Topics: 10
    • Replies: 5
    • ☆

    Thank you Ken.

    I still have P3 and F3 remaining, but I found both are very technical in context.

    I found it very difficult to understand the interest rate risk and exchange rate risks chapters.

    Would you have any recommendations? I really wish to complete the strategic level before the change of syllabus.

    thanks,
    Kenneth

    May 27, 2019 at 11:02 am #517525
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10648
    • ☆☆☆☆☆

    Interest rate risk is tricky. Have you looked at our notes and lectures? I think that once you grasp that the price of an interest rate future is:

    100 – interest rate

    you can make a fair stab at working out, what to do using logic. However, I must confess that even after teaching this material for years I still find that I can mess up!

    Remember that there are unlikely to be more than a couple of OT questions in teh exam on this topic.

    October 19, 2019 at 3:17 pm #550187
    dsodha
    Participant
    • Topics: 18
    • Replies: 13
    • ☆

    Referring to the IRR question above.

    Please help me understand why the IRR is lower and not higher than the cost of capital by 1.25%.

    Surely to lower the NPV from 100 000 to 0 we have to increase the discount rate so that the PV of the cash flows reduce to make NPV 0.

    October 21, 2019 at 7:53 am #550321
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10648
    • ☆☆☆☆☆

    As I said in my reply above, I think this whole question is messed up. It makes no sense to me.

  • Author
    Posts
Viewing 6 posts - 1 through 6 (of 6 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Kaplan ACCA Free Trial

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • zurapirveli@gmail.com on Equity settled share based payments – goods – ACCA (SBR) lectures
  • Sid24012003 on Intangibles – Example 2 – ACCA Financial Reporting (FR)
  • Ken Garrett on CIMA BA1 Spearman’s rank correlation coefficient
  • Ana1674 on CIMA BA1 Spearman’s rank correlation coefficient
  • tehreem21 on MA Chapter 2 Questions Sources of Data

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in