Skip to content
ACCA exam results — Are you ready?Chat about it >>

CIMA Forums

CIMA P3 Exam Practice Kit Q256 IRR

KKen7y ago
Hi tutor, I am confused by the answer to Q256. Why would be discount rate reduced by 1.25% the NPV would fall to zero? I thought it should be the rise in discount rate, which would make the NPV fall. Thanks, Student Question: Q Co is going to invest in a new piece of machinery that will cost $8,000,000. The discount rate of the project is 15% and the PV of the tax shield is $100,000. What is the IRR? Give your answer as a % to 2 decimal places _____________% Answer: 256 14.81 The IRR is the discount rate where the NPV falls to zero. It is a really a sensitivity calculation, the questions we need to ask ourselves are as follows: (1) How much would the NPV need to change by? 100,000 (2) What is this as a % of the investment? 100,000/8,000,000 × 100 = 1.25% So if the discount rate reduced by 1.25% the NPV would fall to zero. IRR = 15% × 98.75% = 14.8125 Answer: 14.81.
kengarrettkengarrettTutor7y ago#1
It confuses me too. The tax shield is present value of tax relief on debt interest payments evaluated at the pre-tax cost of debt and is used in APV calculations. We are not told the NPV of the project at 15%, nor its APV (though that would be $100,000 higher than the NPV). The NPV could be $20,000,000 - we don't know and the IRR of that project would be very high indeed! I think the whole question is messed up.
KKen7y ago#2
Thank you Ken. I still have P3 and F3 remaining, but I found both are very technical in context. I found it very difficult to understand the interest rate risk and exchange rate risks chapters. Would you have any recommendations? I really wish to complete the strategic level before the change of syllabus. thanks, Kenneth
kengarrettkengarrettTutor7y ago#3
Interest rate risk is tricky. Have you looked at our notes and lectures? I think that once you grasp that the price of an interest rate future is: 100 - interest rate you can make a fair stab at working out, what to do using logic. However, I must confess that even after teaching this material for years I still find that I can mess up! Remember that there are unlikely to be more than a couple of OT questions in teh exam on this topic.
DDAMINI6y ago#4
Referring to the IRR question above. Please help me understand why the IRR is lower and not higher than the cost of capital by 1.25%. Surely to lower the NPV from 100 000 to 0 we have to increase the discount rate so that the PV of the cash flows reduce to make NPV 0.
kengarrettkengarrettTutor6y ago#5
As I said in my reply above, I think this whole question is messed up. It makes no sense to me.
Sign in to reply to this topic.