• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

CIMA P3 Exam Practice Kit Q256 IRR

Forums › Ask CIMA Tutor Forums › Ask CIMA P3 Tutor Forums › CIMA P3 Exam Practice Kit Q256 IRR

  • This topic has 5 replies, 3 voices, and was last updated 5 years ago by Ken Garrett.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • May 27, 2019 at 3:12 am #517463
    hkkwu
    Participant
    • Topics: 10
    • Replies: 5
    • ☆

    Hi tutor,

    I am confused by the answer to Q256. Why would be discount rate reduced by 1.25% the NPV would fall to zero? I thought it should be the rise in discount rate, which would make the NPV fall.

    Thanks,
    Student

    Question:
    Q Co is going to invest in a new piece of machinery that will cost $8,000,000. The discount
    rate of the project is 15% and the PV of the tax shield is $100,000.
    What is the IRR? Give your answer as a % to 2 decimal places
    _____________%

    Answer:
    256 14.81
    The IRR is the discount rate where the NPV falls to zero.
    It is a really a sensitivity calculation, the questions we need to ask ourselves are as follows:
    (1) How much would the NPV need to change by? 100,000
    (2) What is this as a % of the investment? 100,000/8,000,000 × 100 = 1.25%
    So if the discount rate reduced by 1.25% the NPV would fall to zero.
    IRR = 15% × 98.75% = 14.8125
    Answer: 14.81.

    May 27, 2019 at 8:46 am #517497
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10583
    • ☆☆☆☆☆

    It confuses me too.

    The tax shield is present value of tax relief on debt interest payments evaluated at the pre-tax cost of debt and is used in APV calculations. We are not told the NPV of the project at 15%, nor its APV (though that would be $100,000 higher than the NPV).

    The NPV could be $20,000,000 – we don’t know and the IRR of that project would be very high indeed!

    I think the whole question is messed up.

    May 27, 2019 at 9:46 am #517515
    hkkwu
    Participant
    • Topics: 10
    • Replies: 5
    • ☆

    Thank you Ken.

    I still have P3 and F3 remaining, but I found both are very technical in context.

    I found it very difficult to understand the interest rate risk and exchange rate risks chapters.

    Would you have any recommendations? I really wish to complete the strategic level before the change of syllabus.

    thanks,
    Kenneth

    May 27, 2019 at 11:02 am #517525
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10583
    • ☆☆☆☆☆

    Interest rate risk is tricky. Have you looked at our notes and lectures? I think that once you grasp that the price of an interest rate future is:

    100 – interest rate

    you can make a fair stab at working out, what to do using logic. However, I must confess that even after teaching this material for years I still find that I can mess up!

    Remember that there are unlikely to be more than a couple of OT questions in teh exam on this topic.

    October 19, 2019 at 3:17 pm #550187
    dsodha
    Participant
    • Topics: 18
    • Replies: 12
    • ☆

    Referring to the IRR question above.

    Please help me understand why the IRR is lower and not higher than the cost of capital by 1.25%.

    Surely to lower the NPV from 100 000 to 0 we have to increase the discount rate so that the PV of the cash flows reduce to make NPV 0.

    October 21, 2019 at 7:53 am #550321
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10583
    • ☆☆☆☆☆

    As I said in my reply above, I think this whole question is messed up. It makes no sense to me.

  • Author
    Posts
Viewing 6 posts - 1 through 6 (of 6 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Rajpoot on FA Chapter 5 Questions IAS 37 – Provisions, Contingent Liabilities and Contingent Assets
  • bizuayehuy on Foreign exchange risk management (1) Part 1 – ACCA (AFM) lectures
  • effy.sithole@gmail.com on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • kyubatuu on MA Chapter 6 Questions Inventory Control
  • hhys on PM Chapter 14 Questions More variance analysis

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in