• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Article on Investment Appraisal and real options

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Article on Investment Appraisal and real options

  • This topic has 11 replies, 4 voices, and was last updated 9 years ago by John Moffat.
Viewing 12 posts - 1 through 12 (of 12 total)
  • Author
    Posts
  • February 25, 2016 at 2:37 pm #302036
    Maja
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    Dear Sir,
    In example 1 delaying the decision to undertake the project they say that after considering option to delay the company can bid 9,6 (value of call option) instead of 5,8 (project’s NPV). Could you please explain why they don’t add value of option to delay to the value of the project?
    Thank you.

    February 25, 2016 at 7:55 pm #302069
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54662
    • ☆☆☆☆☆

    The value of the option includes the intrinsic value of the project.

    February 27, 2016 at 9:28 am #302304
    Maja
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    Thank you. Could you please explain what is the difference between this example where value of the project is the value of the option to delay and Digunder Dec 07 where overall Value of the Project is Project NPV plus the value of the delay option?

    February 27, 2016 at 10:16 am #302311
    jigsaw1992
    Member
    • Topics: 25
    • Replies: 70
    • ☆☆

    pending johns reply, i think i understand wat u meant and since we all one acca family i might just help

    the first example its a mutually exclusive situation, they must undertake the investment now or delay till the future so they choose one either to invest now or in 2 years time and since in 2 years time option valuation gives the higher npv thats what theyll obviously choose.

    the second and third examples are not mutually exclusive. the company can enjoy both npvs.
    they can undertake investment and get that option to sell it at the end of its usefull life or they can undertake investment and pursue a follow on project also simultaneously in 2 years. so theyll enjoy both npvs so for that reason we add.

    I hope this answers your question.

    February 27, 2016 at 10:28 am #302312
    Maja
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    Thank you but actually I tried to compare example 1 from article dealing with option to delay to exam question Digunder from December 2007 also dealing with option to delay a Project. In the answer in my BPp book they say that the overall value of the Project is its NPV plus the option to delay.

    February 27, 2016 at 1:07 pm #302323
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54662
    • ☆☆☆☆☆

    The examiners answer to Digunder was wrong, and BPP have not changed the answer in their Revision Kit. (Kaplan have changed their answer).

    The value of the option is the difference between the NPV using the Black Scholes formula, and the original NPV with no option.

    (My lecture on real options is wrong in this respect – I was following the original exams answer but I will re-record it because of the above point.)

    February 27, 2016 at 1:09 pm #302326
    Maja
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    Nie it is perfectly clear. Thank you.

    February 27, 2016 at 8:56 pm #302351
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54662
    • ☆☆☆☆☆

    You are welcome 🙂

    April 26, 2016 at 4:33 pm #312752
    Binh
    Member
    • Topics: 41
    • Replies: 78
    • ☆☆

    Dear Sir,

    Sorry for coming back this old topic! I also have same question, but now is the case in Q4 June 2011. In the answer, overall NPV = option value (BSOP) + NPV without option to delay. But in the example 1 of ACCA technical article “Investment appraisal and real options”, the option value is compared with the NPV without option! I am confused between these 2 answers.

    April 26, 2016 at 6:52 pm #312776
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54662
    • ☆☆☆☆☆

    There has been confusion because the examiner in June 2011 originally got the answer wrong, and my lecture is wrong as a result (and, I think, the BPP Revision KIt answer is wrong (because it is a copy of the examiners original answer).

    The value using the Black Scholes model is the NPV including the option.
    If you subtract from this the NPV without the option,then the remainder is the value of the option itself.

    April 27, 2016 at 5:15 am #312806
    Binh
    Member
    • Topics: 41
    • Replies: 78
    • ☆☆

    OK, tks you sir! It is clear now!

    April 28, 2016 at 11:59 am #312932
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54662
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 12 posts - 1 through 12 (of 12 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Nashra30 on CIMA E1 Chapter 3 Test
  • azubair on Financial Performance Measurement – ACCA Performance Management (PM)
  • j.akshaya on Group SFP – Example (Basic consolidation) – ACCA Financial Reporting (FR)
  • rishitxx on ACCA BT Chapter 1 – The nature and structure of organisations – Questions
  • singhjyoti on Basic group structures – SPLOCI introduction and example – ACCA (SBR) lectures

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in