• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

Specially for OpenTuition students: 20% off BPP Books for ACCA & CIMA exams – Get your BPP Discount Code >>

Activity based costing – question

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Activity based costing – question

  • This topic has 5 replies, 2 voices, and was last updated 1 year ago by John Moffat.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • December 13, 2021 at 1:40 pm #644168
    Natasha1996
    Member
    • Topics: 34
    • Replies: 22
    • ☆☆

    Hello John.

    I would appreciate your help with this question.

    There are two products R and S:

    Products—————————————–R————–S
    Production units—————————-80000——–60000
    Batch size units——————————100————50
    Machine setup per batch——————–3————–3
    Processing time per unit (minutes)—-3 mints——5 mints

    Costs Pool:
    Machine setup cost——-$180000
    Processing——————$108000
    Order cost——————-$150000
    Inspection cost————-$120000
    Total overheads————$558000

    Overhead Absorption rate:
    This is the rate that is used to absorb or allocate the fixed costs related to each product.

    OAR = Total Overheads / Total Cost driver

    1) Machine setup cost:
    OAR = $180,000 / 450 = $400 per machine setup per batch

    2) Processing cost:
    OAR = $108,000 / 9000 = $12 per processing time per hour

    3) Order cost:
    OAR = $150,000 / 150 = $1000 per batch

    4) Inspection cost:
    OAR = $120,000 / 140,000 = $0.857

    Absorb overhead to each product:

    1) Machine setup cost
    Product R = $400 x 300 batch = $120,000
    Product S = $400 x 150 batch = $60,000

    2) Processing cost
    Product R = $12 x 4000 hour = $48,000
    Product S = $12 x 5000 hour = $60,000

    3) Order cost
    Product R = $1000 x 100 hour = $100,000
    Product S = $1000 x 50 hour = $50,000

    4) Inspection cost
    Product R = $0.857 x 80000 hour = $68,560
    Product S = $0.857 x 60000 hour = $51,420

    Is that all correct?

    December 13, 2021 at 4:37 pm #644189
    John Moffat
    Keymaster
    • Topics: 56
    • Replies: 51952
    • ☆☆☆☆☆

    1. Machine set up cost. There are 800 + 1,200 = 2,000 batches (not 450).

    2. The total processing time is ((80,000 x 3) + (60,000 x 3)) / 60 = 60 hours (not 9,000 hours).

    3. There is not enough information in the question to know how to absorb either the order cost or the inspection cost.

    December 13, 2021 at 6:27 pm #644194
    Natasha1996
    Member
    • Topics: 34
    • Replies: 22
    • ☆☆

    Sorry I do not understand it ’cause the correct cost drivers are as follows:

    The correct cost driver for machine setup cost is machine setups per batch:
    Total Machine setups : (100 x 3) + (50 x 3) = 450

    The correct cost driver for processing cost is processing time per unit:
    Total Processing time in hours : (80000 x 3/60) + (60000 x 5/60) = 9000 hours

    OR we can do this way (both gives same answer)
    Total Processing time in hours : (80000 x 3) + (60000 x 5) / 60 = 9000 hours

    The correct cost driver for order cost is batch size:
    Total Batches : 100 + 50 = 150

    The correct cost driver for inspection cost is production units:
    Total production units = 80000 + 60000 = 140,000

    1) You said that machine setup cost is absorbed using batches but you didn’t see the machine setup per batch (which is the correct cost driver) is already given above.

    2) I am afraid you are mistaken in calculating total processing time here because the correct answer is 9000 hours just the way I calculated above. You took 3 instead of 5 minutes for product S

    Please tell me where I am wrong and why?

    December 14, 2021 at 7:16 am #644209
    John Moffat
    Keymaster
    • Topics: 56
    • Replies: 51952
    • ☆☆☆☆☆

    Machine set-ups:

    I did see that the machine set up per batch was given,
    However there are not 100 batches of product R. 100 is the batch size and therefore the number of batches is 80,000/100 = 800 and similarly there are 60,000/50 batches of S.

    Processing cost:

    You are correct in that I took the wrong figure by mistake. The total processing time is ((80,000 x 3) + (60,000 x 5))/60 = 9,000 hours. Sorry 🙁

    However, again, I am puzzled as to why you are attempting a question for which you do not have an answer 🙂

    December 14, 2021 at 9:01 am #644222
    Natasha1996
    Member
    • Topics: 34
    • Replies: 22
    • ☆☆

    According to your answer, we need a number of batches to calculate total machine setups as a cost driver for machine setup costs like this:

    1) Machine cost:
    Total number of batches = (80000 / 100) + (60000 / 50) = 2000

    But since the cost driver for machine setup costs is machine setup per batch. we need to calculate total machine setups.

    Total machine setups:
    Product A = (800 batch x 3 setups) = 2400
    Product B = (1200 batch x 3 setups) = 3600
    Total machine setups = 6000

    Overhead absorption rate = $180,000 / 6000 = $30 per machine setups

    Absorb overhead to each product:
    Product A = $30 x 2400 = $72,000
    Product B = $30 x 3600 = $108,000

    It is correct now SIR?

    December 14, 2021 at 3:39 pm #644245
    John Moffat
    Keymaster
    • Topics: 56
    • Replies: 51952
    • ☆☆☆☆☆

    Yes, that is correct 🙂

  • Author
    Posts
Viewing 6 posts - 1 through 6 (of 6 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

ACCA News:

Changes to the SBL exam from September 2023

ACCA My Exam Performance for non-variant Applied Skills exams is available NOW

NEW! Download the ACCA Pass Guide

FREE Verifiable CPD for ACCA Members

ACCA mock exams and debrief videos

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

 

Donate

If you have benefited from OpenTuition please donate.

ACCA CBE 2023 Exams

Instant Poll * How was your exam, and what was the result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Specially for OpenTuition students

20% off BPP Books

Get BPP Discount Code

Latest comments

  • Liz7827636 on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Patrickizzo on Accounting for overheads part 3 – ACCA Management Accounting (MA)
  • John Moffat on Investment Appraisal Under Uncertainty: Sensitivity Analysis (example 1) – ACCA Financial Management (FM)
  • DIVIJ on Investment Appraisal Under Uncertainty: Sensitivity Analysis (example 1) – ACCA Financial Management (FM)
  • mohamedrashedalansari on Basic group structures – Impairment – ACCA (SBR) lectures

Copyright © 2023 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in


We use cookies to show you relevant advertising, find out more: Privacy Policy · Cookie Policy