Forum Replies Created
- AuthorPosts
- August 22, 2025 at 7:50 am #718904
Because it relates to a graph and says quantify your answer
Kaplan must have decided not to disclose an answer to this.August 19, 2025 at 9:41 pm #718858Watching all the videos
Working through the open tuition notes
Have a good text book for reference
Work through as many questions as you can – from an exam kit and the ACCA hub
This should prepare you wellAugust 19, 2025 at 7:12 am #718837No the variances is based on the actual units produced at the standard
AQ. AP
Gives you price
AQ. SP
Gives you usage
Au * SQ * SP
It’s a flexed concept
What did we actually make!
Watch John’s video on this
Try to move on from this
It’s a 2 mark questionThe favourable material usage variance means that we used less material than expected which could have been caused by reduced levels of wastage in the production process.
August 18, 2025 at 10:27 pm #718834The answer is in the book
Measures whether more or less material than expected during production, and it’s a key part of variance analysis.
It’s calculated by comparing the actual amount of material used to the standard amount that should have been used, based on actual production output, and then multiplying the difference by the standard cost per unit of material.
Usage looks at the……Difference between
AQ at Std Price
Std qty at Std PriceAQ. SP
408.5 / 152 / 10
1.80 / 2.2 / 20
735.30 / 334.4 / 200
= 1269.70
SQ SP – 950 @ 1.34 = 1273
Is 3.3F
August 17, 2025 at 9:49 pm #718817The solid line of the Period 5 PV chart typically represents the cumulative profit/loss as each product’s contribution is added to the sales mix.
The average profit which will be earned from the sales of three products in this mix.This is because the profit-volume chart illustrates how profits change with varying levels of sales, and the solid line reflects the average profit derived from the combined contributions of the products being sold.
Each product contributes to the overall profit, and the average profit line helps visualise the profitability of the sales mix over the specified period.
August 17, 2025 at 9:43 pm #718816The relevant cost statement for the engineers’ costs should include the penalty of $500 for missing the contractual deadline on Contract X.
The salaries of the engineers are considered sunk costs and therefore irrelevant, as they will be paid regardless of whether they work on this contract or not.
Since there is no other work scheduled for the engineers in that week, the lost contribution from Contract X is not considered relevant because the engineers will still be able to complete it later.
Thus, the only additional cost incurred is the penalty for the delay.
August 17, 2025 at 9:30 pm #718815To calculate the labour rate operational variance for product MN, we need to compare the actual labour rate with the revised standard labour rate.
Budgeted Labour Rate: $8 per hour
Actual Labour Rate:
8×1.25=10 per hour (due to the 25% inc)
Actual Labour Hours: 798,000 / $10 = 79,800 hours
Labour Rate Variance = (10?8) × 79,800
So it is 2×79,800=159,600 Adverse
Thus, the labour rate operational variance for product MN for the last quarter is $159,600 Adverse.August 17, 2025 at 9:19 pm #718814The correct approach is to consider the total savings and how they affect the overall loss.
Total Loss:
(100m)+(10m) = $(110m)If the overall savings from closing Division A are $75m then
Revised total divisional loss:
(110m)-75m = $(35m)
Thus, the revised total divisional net loss is indeed $35m, as stated in the answer you provided.August 17, 2025 at 9:09 pm #718813Option D, is consistent because TOC emphasises maximising throughput while minimising operating expenses.
By keeping conversion costs low, organisation’s can improve their overall efficiency and profitability.
This focus on minimising costs aligns with the TOC principle of optimising the system’s performance by addressing constraints and ensuring resources are used effectively.August 17, 2025 at 9:04 pm #718812While JIT is a pull system that aims to produce only when there is an order, having a reliable forecast helps in planning and timing orders to avoid stockouts and production delays.
Thus all three components are integral to the effective functioning of a JIT system.August 17, 2025 at 9:15 am #7187941. Starting cash balance
Begin with starting cash balance as of April. This is the amount of cash they had on hand at the beginning of the budgeting period.2. Cash inflows
Project the cash inflows for each month (April, May, June).
* Cash Sales: Revenue received directly from sales.
* Collections from Accounts Receivable: Cash received from outstanding invoices.
* Other Income: Any other cash receipts like loans, interest income, or asset sales.3. Cash outflows
Estimate anticipated cash outflows for each month. This includes
* Operating Expenses: Regular expenses like rent, utilities, and payroll.
* Purchases: Payments for inventory or materials.
* Loan Repayments: Principal and interest payments on outstanding loans.
* Capital Expenditures: Payments for new equipment or other investments.
* Other Expenses: Any other expected cash payments.4. Net cash flow
Calculate the net cash flow for each month by subtracting total cash outflows from total cash inflows.5. Ending cash balance
Finally, the ending cash balance for each month by adding the net cash flow to the beginning cash balance. The ending balance for one month becomes the beginning balance for the next month.August 17, 2025 at 9:09 am #718793What is your question?
There is no point writing out a whole question expecting an answer.
You should have an answer in your textbook
August 17, 2025 at 9:07 am #718792Batch Sizes and Mixing Times:
B take 20 m per b of 40 units
M 16 m per b 30 u
C 12 m per b 20 uThroughput Calculation:
B 1.50 – (0.25 + 0.40 + 0.15) = 0.70
M 1.40 – (0.15 + 0.45 + 0.20) = 0.60
C 2.00 – (0.25 + 0.50 + 0.30) = 0.95Throughput per Minute:
B 0.70 / 20 = 0.035
M 0.60 / 16 = 0.0375
C 0.95 / 12 = 0.0792Ranking by Throughput per Minute:
* C, M, BProduction Plan:
To maximise profit, we should first meet the minimum demand:
1 batch of C (20 units) = 12 minutes
1 batch of M (30 units) = 16 minutes
1 batch of B (40 units) = 20 minutesThis totals 48 minutes, leaving 72 minutes available.
After fulfilling minimum demand, we can produce more Cupcakes and Muffins:
Produce 5 batches of C (100 units) = 60 minutes
Then 1 batch of M (30 units) = 16 minutes
This totals 76 minutes, which exceeds the available 72 minutes.The best combination that fits within the 120 minutes while maximizing profit is:
80 B (2 batches) = 40 minutes
30 M (1 batch) = 16 minutes
100 C (5 batches) = 60 minutesTotal = 40 + 16 + 60 = 116 minutes.
Thus, the optimal production plan for Wednesday is A) 80 brownies, 30 muffins, and 100 cupcakesAugust 17, 2025 at 8:57 am #718790The mixing process is the bottleneck with only 120 minutes available, we need to analyse the throughput of each product and the time required for mixing. Follow a process with throughput:
1. Batch Sizes & Mixing Time
2. Throughput Calculation
3. Throughput per Minute
4. Ranking by Throughput per Minute
5. Production Plan
6. Maximising Remaining Time
7. Final Optimal Production Plan
Thus, the optimal production plan for Wednesday
is A) 80 brownies, 30 muffins, and 100 cupcakes.August 16, 2025 at 10:15 pm #718785Why are you spending so much time on 2 mark questions?
August 16, 2025 at 10:13 pm #718784So the conversion of hours to minutes allows for a more comprehensive calculation, making it easier to understand the time required for production relative to the available operational time.
You convert hours to minutes to make the calculations more precise. Since the process is operational for 8 hours per day, this translates to 480 minutes (8 hours x 60 minutes/hour).August 15, 2025 at 5:12 am #718770Yes, they are
Have a look at the ACCA FM syllabusAugust 14, 2025 at 9:19 pm #718762The correct forward exchange rate that ensures neither a loss nor a gain is calculated using the interest rate parity formula:
1.415 * 1.02 / 1.018 = 1.418E rate * 1+ I rate 1st / I rate 2nd
1st rate is euroYour calculation of 1.412 is close but does not account for the interest rate parity correctly.
The forward rate of 1.418 ensures that when you convert the future euros back to dollars, you will receive an amount equivalent to the dollar investment, confirming that the investor makes neither a loss nor a gain.
August 14, 2025 at 8:56 pm #718758This is in the wrong area
August 14, 2025 at 8:50 am #718747The maintenance costs of $20,000 per annum are payable by the lessor at the end of each year. Since these costs are incurred by the lessor, they are not directly tax-deductible for the lessee. However, the tax implications arise from the tax relief on these maintenance costs.
The tax relief on the maintenance costs is based on the corporation tax rate of 25%. Therefore, the tax savings from the maintenance costs for each year is calculated as 20000 * 0.25 = 5000
The tax savings are realised in the year following the maintenance payment.
Thus, the tax savings for years 2 to 6 are discounted back to present value using a discount rate of 6%.
The annuity factor for 5 years at 6% is 4.212, and the present value of the tax savings is calculated 5,000 * 4.212 = 21,060
The net present value of the maintenance cash flows, after considering the tax savings, is calculated by subtracting the present value of the maintenance costs from the present value of the tax savings.
The treatment of maintenance and tax involves recognising the maintenance costs as a cash outflow and calculating the tax savings from these costs, which are then discounted to present value to assess their impact on the overall financial analysis.
So the NPV provides insight into the net effect of these cash flows, allowing for better decision-making regarding the lease.
This is all explained with examples in my johns lectures. The lectures are a complete free course for Paper FM and cover everything needed to be able to pass the exam well.
Please watch them
August 12, 2025 at 9:53 pm #718733It is very difficult for me to say.
Depends how much work you put in.
Knowledge is very important. Practice is critical!If you use kaplan’s study text notes, open tuition notes and the study hub you should be well prepared.
As long as you practice what you have learned with questions.August 11, 2025 at 8:05 am #718707Yes, you are correct. The total fixed costs remain unchanged regardless of the increase in production volume. The fixed OAR is calculated by dividing the total fixed overheads by the total hours worked. If the number of hours worked increases, while the total fixed overheads stay the same, the OAR will decrease.
This means that unless the question explicitly states that there is an increase in total fixed costs due to specific circumstances, we assume that the total fixed costs do not change with an increase in volume.
The increase in volume does not lead to an increase in fixed costs; it only affects the allocation of those fixed costs across a larger number of hours. Therefore, the assumption is that fixed costs remain constant unless otherwise specified in the question.
August 10, 2025 at 9:36 pm #718704The relevant cash flow is:
Extra variable overheads: 450 hours × $4/hr $1,800
Rent $1,200
Total $3,000
Fixed costs are not incremental and idle time would normally mean that the machines are not in use are so are not an incurred cost.Regarding your question about the 500 incremental labour hours, they are not included in calculating fixed overhead costs because they are considered incremental and do not lead to an increase in fixed overheads, which are typically absorbed based on normal capacity. The fixed overhead absorption rate applies to the normal level of activity, and any additional hours beyond that do not incur additional fixed costs.
August 10, 2025 at 9:31 pm #718703This definition accurately reflects the essence of standard costing, which involves comparing the actual costs incurred during a specific period with the predetermined standard costs that are set based on expected levels of activity.
The purpose of this comparison is to analyse variances, which helps organisations assess their performance and identify areas for improvement.
Option B, while it mentions predetermined costs, implies a broader comparison of actual results against these costs without specifically focusing on the level of activity, which is a key aspect of standard costing.
August 9, 2025 at 9:22 pm #718694In Example 8, the minimum transfer price is calculated as the marginal cost plus any lost contribution. In this case, the marginal cost is $70, and the lost contribution is determined by the opportunity cost of not selling externally.
To make transfers of Y worthwhile, A need to charge at least 70 + (10 × 4) = $110 p.u.
The lost contribution reflects the opportunity cost of not selling the product externallyHopefully that explains it :0-)
- AuthorPosts