Forum Replies Created
Viewing 3 posts - 1 through 3 (of 3 total)
- AuthorPosts
- January 30, 2023 at 1:08 pm #677622
How is the machine set up costs calculated in part a?
The working says machine set – up costs for K is (26k – 4K) * 500/400.I don’t understand why it is multiplied by 500 then divided by 400 and not multiplied by 400 / 500
Please could you help me understand this?
September 19, 2022 at 9:18 am #666709This question is from the ACCA Practice Test Papers
Sorry, so if I understand correctly the correct working out is: (4000+200-300)/1000. So the answer is 3.9. Is that correct?
September 18, 2022 at 4:36 pm #666688Sorry there was a typo. The solution said (4000-200+300)/1000. But I don’t understand why.
I thought actual cost was 4000 so we had to work backwards using the variance to calculate the standard direct material cost per unit i.e. (4000+200-300)/1000?
- AuthorPosts
Viewing 3 posts - 1 through 3 (of 3 total)