APVForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › APVThis topic has 1 reply, 2 voices, and was last updated 14 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts June 1, 2010 at 7:46 pm #44338 dongbulaMemberTopics: 5Replies: 7☆Hi, Should we include any indirect cost into our cash flow caculations?Thanks! June 3, 2010 at 11:33 am #61836 John MoffatKeymasterTopics: 57Replies: 54500☆☆☆☆☆If it involves an extra cash flow to the company, then yes.All variable overheads/indirect costs will be included because they are by definition extra costs.Fixed overheads/indirect costs will only be included if the total is going to change as a result of doing the project.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In