POPIT and ProjectForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA SBL Exams › POPIT and ProjectThis topic has 1 reply, 2 voices, and was last updated 7 years ago by Ken Garrett.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts December 4, 2017 at 4:46 pm #420290 abdulahad92MemberTopics: 17Replies: 36☆☆Sir, should the elements of POPIT be considered before or after the change? Secondly, is the benefit owner the project sponsor also? December 4, 2017 at 10:32 pm #420441 Ken GarrettKeymasterTopics: 10Replies: 10544☆☆☆☆☆POPIT should be considered before the change. These are the elements that have to be considered.Benefit owner is the person responsible for delivering the benefits eg getting maximum efficiency from a new system.Project sponsor is tne person or department behind the project, pushing for it and usually paying for it.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In