There are three processes 1, 2 and 3 , DAILY HOURS AVIALBLE FOR P1 ARE 22 HOURS, P2 ARE 22 HOURS AND P3 ARE18 HOURS. TIME FOR one unit of X IN P1 IS 1 HOURR, P2 IS 0.75 HOUR AND P3 IS1 HOUR Time FOR one unit of Y IN P1 IS 0.75 HOUR, P2 IS 1 HOUR AND P3 IS 0.5 HOUR
Daily demand OF X IS 10 UNITS AND OF Y IS 16 UNITS what the bottleneck process? kindly help
The time needed in P1 is (10 x 1) + (16 x 0.75) = 22 hours The time needed in P2 is (10 x 0.75) + (16 x 1) = 23.5 hours The time needed in P3 is (10 x 1) + (16 x 0.5) = 18 hours
It is only P2 where there are not enough hours available, and so P2 is the bottleneck.
(Why are you attempting questions for which you do not have an answer? You should be using a Revision Kit from one of the ACCA approved publishers – they are answers and workings!)