Yield Variance QuestionForums › ACCA Forums › ACCA PM Performance Management Forums › Yield Variance QuestionThis topic has 2 replies, 2 voices, and was last updated 3 years ago by John Moffat.Viewing 3 posts - 1 through 3 (of 3 total)AuthorPosts August 23, 2021 at 3:22 pm #632629 mathygreenMemberTopics: 1Replies: 2☆Hi SirI am getting confused in the question below, can you please help me solve itA chemical flavouring, product C is made by mixing two materials together:Standard – Kg per batch – $ per kg – $ per batchL – 300 – $1.30 – 390 H – 500 – $2.82 – 1,410Input per batch 800kg10% standard loss 80kgOutput per batch 720kgFor batch 1247 input as 250.5kg of L and 669.5kg of H. Output from the batch was 810kg of product C.What is the yield variance?I am getting confused with the 10% loss part.Thank you in advance! ______________________________ August 23, 2021 at 3:24 pm #632630 mathygreenMemberTopics: 1Replies: 2☆I understood my mistake.Sorry, for the trouble.Thank you! August 23, 2021 at 5:43 pm #632648 John MoffatKeymasterTopics: 57Replies: 54641☆☆☆☆☆No problem, and I am pleased you are now sorted out 🙂AuthorPostsViewing 3 posts - 1 through 3 (of 3 total)The topic ‘Yield Variance Question’ is closed to new replies.